- Step 1: define what the renovation must achieve
- Step 2: inspect the property and its documents
- Step 3: build the budget from ranges, then from a fixed quote
- Step 4: check VAT, licences and the community
- Step 5: plan the timeline
- Step 6: prepare the property and your life
- A worked budget example for a 90 m² flat
- Paying for a renovation: how to structure it
- Questions to ask before you sign
- Planning a renovation from abroad
- Common mistakes when planning a renovation
- When to call a professional
- Next step
Where to start: scope, then money, then time
Plan a renovation in this order: decide the scope, set the budget from realistic ranges, check the permissions and only then fix the dates. Most renovations that go over budget or over time did the steps in the wrong order: they chose finishes before checking what was behind the walls, or booked a start date before asking whether the work needed a licence.
For a full flat in Alicante, the usual figures are €450 to €900 per m², VAT not included, and 8 to 14 weeks on site for a flat of 70 to 100 m². Houses and villas run at €600 to €1,200 per m² and 3 to 6 months. A bathroom costs €5,500 to €12,000 in 2 to 3 weeks, and a kitchen €7,000 to €18,000 in 3 to 5 weeks. Use these as the first layer of your plan, and replace them with a fixed quote as soon as you can.
| Project | Cost guide (VAT not included) | Time on site |
|---|---|---|
| Full flat renovation | €450 to €900 per m² | 8 to 14 weeks (70 to 100 m²) |
| House or villa renovation | €600 to €1,200 per m² | 3 to 6 months |
| Full bathroom, 4 to 6 m² | €5,500 to €12,000 | 2 to 3 weeks |
| Small guest WC | €3,500 to €6,000 | Depends on the project |
| Kitchen | €7,000 to €18,000 | 3 to 5 weeks |
| Bath to shower conversion | €950 to €2,200 | 1 to 2 days |
| Commercial premises | €300 to €800 per m² | 4 to 10 weeks |
Step 1: define what the renovation must achieve
Write two lists. The first is the problems the renovation must solve: damp, old wiring, a bathroom that does not work, a kitchen that is closed off, heat in summer. The second is the wishes: a bigger kitchen island, a feature wall, a better terrace. The first list is the project; the second list is what you cut if the numbers do not work. Say who the property is for: living in it, letting it or selling it, because each leads to different choices of finishes and different priorities. See our guides on renovating a flat to rent out and renovating before selling.
Step 2: inspect the property and its documents
The cost of a renovation depends more on what is behind the surfaces than on the finishes you choose. Before you set a budget, check:
- Structure and cracks: read our guides on cracks in walls if you see any.
- Damp: staining, a musty smell or peeling paint; see musty damp smell.
- Electrics: age of the consumer unit, earths, contracted power; see old consumer units.
- Plumbing: the pipe material and the pressure; see lead and iron pipes.
- Roof and terraces: leaks, drainage and waterproofing.
- Documents: the community statutes, the habitation certificate, the licence history and the energy certificate.
If you are buying a property to reform, do this before you commit. A builder's visit is quick and tells you whether the property needs a cosmetic update or a full renovation. Our guide to renovating an old flat in Spain gives the order of work.
Step 3: build the budget from ranges, then from a fixed quote
A good first budget has four layers:
- The works, from per m² or per room ranges, adjusted for the state of the property.
- The finishes you choose, because tiles, kitchens, sanitaryware and flooring can move the total as much as labour.
- Taxes and paperwork: VAT, and the cost of licences or projects where they apply.
- A contingency for what is found once finishes are removed, especially in an older property.
Then ask for a fixed, itemised quote from a company after it has visited the property. A fixed price by item shows what is and is not included, what the materials are and how long each phase takes. Compare scope, not only the total; our guide on how to read and compare a renovation quote explains what to look for. Full per m² benchmarks are in renovation cost per m² in Alicante.
What a contingency is for
A contingency is not padding. It covers items that cannot be seen: pipes that turn out to be corroded behind a wall, a floor slab that needs levelling, damp behind old tiles, wiring that was not as shown. In newer properties the risk is smaller; in a 1960s to 1980s flat it is larger. A fixed quote protects you from price changes on what was quoted, but it cannot price what nobody could see. Ask your builder how they handle discoveries: a clear written procedure for extras, with a price agreed before the work, is a sign of a well-run job.
Step 4: check VAT, licences and the community
VAT. Renovation of a private home more than two years old can qualify for the reduced 10% VAT rate, subject to the conditions, including a limit on the share of materials supplied. Your quote should show the rate applied. See reduced 10% VAT on renovations.
Licences. Most interior works are processed by a declaración responsable or a licencia de obra menor at the town hall, while works that touch the structure, the facade or the use of the building need a project and a licencia de obra mayor. See declaración responsable for building works, minor works licence in Alicante and major works licence. We handle the paperwork for you.
The community of owners. If the property is in a block, the community must be told about works, and anything touching the facade, structure or shared pipes can need its approval. Noise hours apply. See community permission for renovations.
Step 5: plan the timeline
Build the timeline backwards from the date you need the property ready. A realistic plan has these phases:
| Phase | What happens | Notes |
|---|---|---|
| Brief and visit | You define the scope, the builder inspects | Our visit is normally within 48 to 72 hours |
| Quote and decisions | Fixed quote, choice of finishes | Late choices cause delay |
| Permissions | Declaración responsable or licence; community | Can set the start date |
| Ordering | Windows, kitchens and some tiles take time to arrive | Order before the start |
| Works | Strip-out, structure, installations, finishes | 8 to 14 weeks for a 70 to 100 m² flat |
| Snagging and handover | Checks, small corrections, documents | Allow a few days |
The commonest causes of delay are late decisions on materials, deliveries that were ordered too late and permissions that were assumed rather than checked. The works phase itself is usually the most predictable. Our guides on how long a full renovation takes and how long a bathroom renovation takes show the sequence in detail.
Choosing the best time of year
In Alicante you can work all year, but summer heat slows outdoor work and August is a slow month for suppliers and administration, while pool and terrace work is best from October to April. See our guide on the best time of year to renovate in Alicante.
Step 6: prepare the property and your life
Decide where you will live during the works, or whether you can renovate in phases; see living in your home during a renovation. Clear the rooms, protect what stays, agree access and parking for deliveries and a skip; see skip hire and rubble removal. Our guide on how to prepare your home for renovation has a checklist.
A worked budget example for a 90 m² flat
Here is how the ranges turn into a first budget. Our price guide for flats is €450 to €600 per m² for a basic renovation, €600 to €750 for a mid-range one and €750 to €900 or more for a high-end one, VAT not included. For a 90 m² flat that gives these orientative totals before VAT:
| Level | Per m² | Total for 90 m² | What it typically means |
|---|---|---|---|
| Basic | €450 to €600 | €40,500 to €54,000 | New installations where needed, simple finishes |
| Mid | €600 to €750 | €54,000 to €67,500 | Better materials, more bespoke carpentry |
| High | €750 to €900 | €67,500 to €81,000 | High-grade finishes, custom design |
These are simple multiplications, not a quote. Two things then change the real figure: the state of the property (a flat with lead pipes, no earth and damp needs more than one that only needs new finishes) and the choices you make about kitchens, bathrooms and flooring. If the reduced 10% VAT rate applies, add 10% instead of the full rate; if it does not, the standard rate applies, and your quote will show which. Then add a contingency and the cost of any licence or project. The result is the number you should be planning your finances around, not the headline per m² figure.
Paying for a renovation: how to structure it
How you pay matters almost as much as what you pay. Good practice is a written contract with a payment schedule tied to stages of work rather than a large payment up front, with the final payment after the handover and the snag list. Be wary of requests for a large deposit before any work or materials have been delivered, or for cash with no invoice. Ask for invoices that show the VAT rate, because you may need them for the reduced rate, for a future sale or for an insurance claim. If you are paying from abroad, agree the method early and keep every document.
Questions to ask before you sign
- Who is the single person responsible for the job, and how do I reach them?
- Is the quote fixed and itemised, and what happens with extras?
- What is the schedule, and what are the decision deadlines on my side?
- Who handles the licence or declaración responsable, and what does it cost?
- What does the written guarantee cover, and for how long?
- What happens if a delivery is late or the weather stops outdoor work?
Planning a renovation from abroad
Many of our clients plan from the UK or elsewhere. What makes that work is structure: a named project manager, a fixed itemised quote, a written schedule with decision deadlines, finishes chosen from photos and samples, payments tied to stages and photo and video updates through the job. Decide early and in writing, because a decision that waits for your next visit can hold up the whole schedule. A contract that sets out scope, price, timeline and guarantee protects you whether you are on site or not; see what a renovation contract should include.
Common mistakes when planning a renovation
- Setting a date before checking permissions. A licence or community notice can set the start.
- Budgeting from the finishes only. Hidden items often matter more.
- Having no contingency. Any renovation of an older property finds something.
- Comparing quotes by total only. Two quotes for different scopes are not comparable.
- Changing decisions once the walls are open. Late changes cost more than early ones.
- Ordering long-lead items late. Windows and kitchens can be the critical path.
- Not asking who is responsible. One named person should be accountable for the whole job.
When to call a professional
You can write the brief, collect documents, compare finishes and tidy the property yourself. You need a professional for the inspection, the quote, the permissions, the design of the installations and anything that touches the structure, plumbing or electrics. If you want a view before you commit, ask for a free visit and a fixed quote; it costs nothing and is the quickest way to replace estimates with real numbers.
Next step
If you are planning a renovation on the Costa Blanca, we will visit within 48 to 72 hours, or review photos and a video if you are abroad, and give you a fixed, itemised quote and a written schedule. See our full home renovation service, the renovation prices and contact us.
Frequently asked questions
How do I budget for a home renovation in Spain?
Budget from ranges first, then replace them with a fixed quote. In Alicante a full flat renovation costs €450 to €900 per m², a house €600 to €1,200 per m², a bathroom €5,500 to €12,000 and a kitchen €7,000 to €18,000, all VAT not included. Add VAT, licence costs and a contingency for what you cannot see.
How much contingency should I add to a renovation budget?
Keep a reserve for the unexpected, and make it larger for old properties where pipes, wiring, damp and structure are hidden behind finishes. A fixed itemised quote reduces the risk but does not remove it for items that cannot be seen until work starts. We discuss the likely risks on the free visit.
How do I start a home renovation project?
Write down what the renovation must fix, check the condition of the property and its documents, and get a visit and a fixed itemised quote from a company. Then confirm the permissions and agree the schedule and the choice of materials before work starts.
How do I plan a home renovation timeline?
Work backwards from the date you need the property ready, and add the duration of each phase: design and quotes, permissions, ordering materials, works and snagging. A full flat renovation takes 8 to 14 weeks on site for 70 to 100 m², a bathroom 2 to 3 weeks and a kitchen 3 to 5 weeks, but planning and permissions come before that.
Do I need a licence to renovate in Spain?
Most interior works are processed by a declaración responsable or a licencia de obra menor at the town hall, and larger works that touch the structure or the facade need a project and a licencia de obra mayor. In a block you also inform the community. We handle the paperwork.
What is the reduced VAT rate on renovations?
Renovation of a private home more than two years old can qualify for the reduced 10% VAT rate, subject to the conditions, including that materials supplied do not exceed a share of the total. Our quote shows the rate applied, and our guide explains the rule.
Can I plan and manage a renovation from abroad?
Yes, with the right structure: a named project manager, a fixed itemised quote, a written schedule, decisions made from photos and samples, and photo and video updates. Plan your choices early, because late decisions cause most of the delays.