- How long a bathroom renovation takes: the direct answer
- Indicative schedule for a complete bathroom renovation
- Week 1: demolition and services, where the surprises appear
- Week 2: masonry, waterproofing and tiling, where drying rules
- Week 3: installation, finishing and handover
- Bath to shower conversion: why it only takes 1 or 2 days
- What stretches a bathroom renovation and how to avoid it
- Common mistakes
- When to call a professional
How long a bathroom renovation takes: the direct answer
A complete bathroom renovation takes 2 to 3 weeks on site; replacing a bath with a shower tray, 1 to 2 days. These are our indicative timescales for a 4 to 6 m² bathroom in Alicante and the surrounding area, respecting the drying times. If someone promises you a complete bathroom in a week, ask how they intend to dry the screed, the render and the waterproofing.
The duration of a bathroom depends less on its size than on the sequence of trades: demolition, plumbing, electrics, masonry, tiling, suspended ceiling, sanitaryware, screen and painting. Each one needs the previous one to have finished and, at several points, the materials to have dried. That is why a 4 m² bathroom takes almost as long as a 6 m² one: the difference is in the square metres of tiling, not the number of steps.
The indicative price of a bathroom renovation in Alicante is €5,500 to €12,000, VAT not included, for a complete 4 to 6 m² bathroom; a small WC, €3,500 to €6,000. You can see the full price list on our renovation prices page.
Indicative schedule for a complete bathroom renovation
In a 2 to 3 week bathroom renovation, the first week is demolition and services, the second is masonry and tiling, and the third is installation and finishing; the drying times mark where it cannot go faster. The following schedule is indicative and assumes that all materials are on site from day one.
| Days | Phase | What happens | Drying or waiting time |
|---|---|---|---|
| 1 to 2 | Demolition | Protection of common areas, removal of sanitaryware and screen, stripping wall and floor tiles, rubble out | None |
| 2 to 4 | Services | Chasing, new plumbing (hot and cold supply, waste), new electrical circuit and outlets, check or connection to the drainage stack | Pressure test before closing |
| 4 to 6 | Masonry | Closing chases, rendering walls, floor screed with falls to the shower, forming the tray recess or wet-room floor | 1 to 3 days drying depending on thickness |
| 6 to 8 | Waterproofing | Waterproofing the shower area and floor-to-wall junctions | 24 hours or more curing |
| 8 to 12 | Wall and floor tiling | Laying wall and floor tiles, cutting, levelling | 24 to 48 hours before grouting |
| 12 to 13 | Grouting and ceiling | Grouting, cleaning, moisture-resistant plasterboard or plaster ceiling, spotlight | 24 hours |
| 13 to 15 | Installation | Shower tray, toilet, basin and unit, taps, screen, towel radiator, switches and sockets | Silicone: 24 hours without using the shower |
| 15 to 16 | Painting and finishing | Anti-damp paint, accessories, touch-ups, cleaning, testing, handover | None |
If the room is a WC without a shower, waterproofing and part of the tiling are skipped and the timescale drops. If a tiled wet-room floor with falls and microcement is built, days of drying and sealing are added. If a shared drainage stack has to be replaced, coordination with the community is added.
Week 1: demolition and services, where the surprises appear
The first week concentrates demolition and the new water, waste and electrical services; it is the phase where you discover what was behind the tiles, and in older flats in Alicante there is almost always something. That is why we insist on a prior technical visit with a check of the consumer unit, the drainage stack and the condition of the pipes.
Demolition takes one or two days: entrance hall, stairs and lift are protected, sanitaryware and screen are removed, wall and floor tiles are stripped and the rubble is taken out. In communities with strict rules, noise hours and the way rubble is removed set the pace; our guide on community of owners permission for renovations explains what to expect.
Services take two or three days. Chases are cut, the new hot and cold supply is run, the waste pipes are installed with the correct falls to the stack and the new electrical circuit is wired with protected outlets and, if there is a water heater or towel radiator, its own line. Before closing, the water pressure is tested.
In the 1960s to 1980s flats in the Centro, Carolinas, Benalúa or San Blas it is common to find lead or galvanised iron pipes, old wiring with no earth and asbestos cement drainage stacks. Replacing them is essential for the renovation to last, and the quote should allow for it in advance.
Week 2: masonry, waterproofing and tiling, where drying rules
The second week is masonry, waterproofing and tiling, and it is the one that cannot be rushed: the floor screed, the render and the shower waterproofing need to dry before receiving tiles, and the adhesive needs to set before grouting. Skipping those times is the number one cause of hollow-sounding tiles, cracked grout and leaks into the flat below.
The order is this: close the chases and render the walls, screed the floor with a fall to the shower waste, let it dry according to thickness and temperature, waterproof the shower area with a liquid membrane or sheet and the corners with tape, let it cure, and then tile the walls and floor. Tiling a 5 m² bathroom in standard format takes two or three days; with large-format porcelain or herringbone patterns, a little more. Then 24 to 48 hours of setting and grouting.
This is also where the shower is decided: a resin or ceramic tray on the screed, or a tiled wet-room floor with falls and a continuous finish. The wet-room floor looks very good but adds days of drying and sealing. Our guide on bathroom renovation mistakes covers the trade-offs.
In summer in Alicante drying is fast, but ventilation matters; in winter, with high ambient humidity near the sea, times stretch a little. A good project manager adjusts the schedule to that rather than forcing it.
Week 3: installation, finishing and handover
The third week is installation: ceiling, tray, toilet, basin, taps, screen, switches, painting and cleaning; it is the most satisfying phase and where a missing material can stop the job. If the made-to-measure screen or the basin unit has not arrived, the bathroom sits unfinished for days.
The moisture-resistant plasterboard or plaster ceiling is installed with the spotlight and the extractor grille, jointed and left to dry. Then the final plumbing goes in: shower tray or the finish of the wet-room floor, toilet, basin and unit, taps, wastes. The electrician fits switches, sockets, spotlight and, if there is one, the towel radiator or heater outlet. The screen is measured after tiling if it is made to measure, which can mean days of manufacturing; a standard screen is fitted directly. Silicones need 24 hours before the shower is used.
Finally, anti-damp paint on the ceiling and untiled walls, accessories, touch-ups, cleaning and water and electrical tests. Handover includes the installation documents and the written guarantee of the works. For owners who are not in Spain, we send a photo and video record of every stage.
Bath to shower conversion: why it only takes 1 or 2 days
Replacing a bath with a shower tray takes 1 to 2 days because the rest of the bathroom is not touched: the bath is removed, the waste adapted, the tray levelled and installed, the previously hidden area tiled and the screen fitted. It is the most requested bathroom job in Alicante, both for accessibility for older residents and for convenience.
On day 1 the bath and tap are removed, the waste is adapted to the position of the tray (low-profile trays have a shallow trap), the base is levelled, the tray is placed and the strip of wall that was behind the bath panel is tiled, normally with a tile as close as possible to the existing one or with a contrasting band. On day 2 it is grouted, the taps and screen are installed and everything is sealed. Silicones need 24 hours before showering.
The timescale stretches if the bath waste is in a position that means opening more floor, if damp appears under the bath or if the screen is made to measure and has to be manufactured. The indicative price is €950 to €2,200, VAT not included, and includes removal, tray, screen and partial retiling. More detail on our bath to shower conversion in Alicante page.
What stretches a bathroom renovation and how to avoid it
What stretches a bathroom renovation most is starting without all the materials, finding surprises when demolishing, changing decisions halfway through and having to coordinate with the community over a shared drainage stack. Almost all of it is avoided with a good technical visit and by deciding everything before day one.
- Incomplete materials. The tray, screen, sanitaryware, unit, taps and tiles must be on site or have a confirmed delivery date before starting. A tray that arrives on day 10 instead of day 1 forces the whole second week to be reorganised. If you are choosing from abroad, confirm deliveries before the start date is fixed.
- Surprises in older flats. Drainage stack in poor condition, lead pipe, damp in the floor, uneven slab. A visit that checks these points and a quote that includes replacing services avoid most of them.
- Last-minute changes. Moving the basin after the chases are cut, changing the tiles once they are ordered or deciding on a wet-room floor with the tray already bought. Each change costs days.
- Shared drainage stack. If the section running through your bathroom has to be replaced, it must be agreed with the community and sometimes with the neighbours above and below.
- Forced drying. Trying to tile on a damp screed or grout the same day does not shorten the job: it causes snagging and complaints.
- Uncoordinated trades. If you hire a plumber, an electrician and a tiler separately, any one of them missing a day pushes the others back. A single project manager links the trades together.
Common mistakes
- Choosing on the shortest timescale. A complete bathroom in a week is only possible by skipping drying times or items. Ask for a schedule with drying times included.
- Not having the materials on day one. Especially a made-to-measure screen, the tray and the basin unit.
- Not planning where to shower. If it is the only bathroom, organise the alternative before starting; it is not a minor detail for two weeks.
- Forgetting ventilation. A bathroom without a window needs an extractor; deciding it after the ceiling is up means reopening it, and it is the usual cause of mould on the ceiling and grout.
- Leaving the old electrics. If the rest of the bathroom is new and the wiring is from the 1970s, the renovation is incomplete and does not meet the current rules for wet areas.
- Saving on waterproofing. It is the cheapest item in the bathroom and the one that prevents the most expensive problem: a leak into the neighbour below.
- Not checking the shower falls before tiling. A tray or wet-room floor without the correct fall collects water forever.
- Not fixing the timescale and what counts as handover in writing. Snagging, cleaning and testing are part of the works.
When to call a professional
A handy owner can paint, change accessories, replace a tap or a toilet seat. Everything else in a bathroom renovation (services, waterproofing, tiling, replacing a bath with a shower) is best left to professionals, because of the sequence of trades, the drying times and because mistakes come back as leaks.
In addition, the new electrical installation in the bathroom must comply with the Spanish low-voltage regulations (REBT) on protection zones and must be carried out by an authorised installer, and the renovation generally needs a declaración responsable or minor works licence with the town hall, which we handle.
At Costa Renova we do a technical visit within 48 to 72 hours, deliver a fixed itemised quote, handle the municipal procedure, work with a single project manager and give a written guarantee of the works. If you want to know how long your bathroom would take and what it would cost, book the free visit from our bathroom renovation in Alicante page or from the contact page.
Frequently asked questions
How long does a complete bathroom renovation take?
Between 2 and 3 weeks on site for a complete bathroom of 4 to 6 m², according to our indicative timescales. That includes demolition, new services, wall and floor tiling, suspended ceiling, sanitaryware, shower screen and painting, respecting the drying times. A small WC without a shower can be finished somewhat sooner.
How long does it take to replace a bath with a shower?
Between 1 and 2 days. The bath is removed, the waste adapted, the tray installed, the affected area retiled and the screen fitted. It is a quick job because it does not touch the rest of the bathroom. Our indicative price is €950 to €2,200, VAT not included.
Why does a bathroom take two weeks if it is such a small room?
Because five trades work in sequence (demolition, plumbing, electrics, masonry and tiling, sanitaryware installation) and between them there are compulsory drying times: the floor screed, the render, the shower waterproofing and the grout need hours or days before the next step. Rushing them causes tiles that come loose and leaks.
Can I use the bathroom during the renovation?
No, for most of the works. From demolition until the sanitaryware goes in there is no toilet or shower. If it is the only bathroom, arrange an alternative with family, neighbours or a gym, or plan the works so that the toilet is installed provisionally as early as possible. We discuss this at the technical visit.
What delays a bathroom renovation most?
Materials not on site on day one (shower tray, made-to-measure screen, sanitaryware, tiles), surprises when demolishing in older flats (asbestos cement or iron drainage stacks, lead pipes, damp) and changes of mind halfway through. Deciding and receiving everything before starting is the best guarantee of the timescale.
How long do the quote and the start of works take?
We do the technical visit within 48 to 72 hours in Alicante and the surrounding area and deliver a fixed itemised quote after the visit. The start date depends on the materials being chosen and received and on the declaración responsable with the town hall, which we handle. Allow a few weeks between signing and the first day on site.
Do I need a permit to renovate a bathroom in Spain?
Yes, in general a declaración responsable or minor works licence with the town hall, because services and finishes are renewed. Community agreement is not usually needed unless a shared drainage stack is touched. We handle the procedure as part of the renovation.