How long does a full renovation take: realistic timescales phase by phase

Guide · 10 min read · Costa Renova site team · updated

A full renovation of a 70 to 100 m² flat in Alicante takes 8 to 14 weeks on site; a house or villa, 3 to 6 months. On top of that come the weeks beforehand for the quote, the permits and ordering materials. This guide sets out the schedule phase by phase, what stretches it and what you can do, even from abroad, to make sure it is met.

  • Fixed, itemised quote, free and with no obligation
  • Site visit within 48–72 h in Alicante and 45 km around
  • One project manager from start to finish
Illustrative image: living room of a renovated flat
Illustrative image: living room of a renovated flat.
On this page
  1. How long a full renovation takes: the direct answer
  2. Indicative schedule for a full flat renovation
  3. Phase 0: what happens before the works start
  4. Phases 1 and 2: demolition, services and masonry
  5. Phases 3 to 6: finishes, joinery, painting and handover
  6. What stretches a full renovation (and what you can control)
  7. Alicante specifics: older flats, the coast and the heat
  8. Common mistakes
  9. When to call a professional

How long a full renovation takes: the direct answer

A full renovation of a 70 to 100 m² flat takes 8 to 14 weeks on site; a house or villa, 3 to 6 months. These are our indicative timescales for Alicante and the surrounding area, and they do not include the weeks beforehand for the quote, permits and ordering materials. A shorter timescale than that, for a complete renovation with new services, usually means something has been left out or drying times are not being respected.

The duration depends on four things: the floor area, the scope (whether you replace all services and change the layout or only renew finishes), the condition of the building (1960s to 1980s flats in central Alicante produce more surprises than one from the 2000s) and, above all, how well the project is planned before it starts. This guide gives you the schedule phase by phase so you know what to expect each week and what you can do to keep it on track, including if you are managing the project from the UK or Ireland.

The reference prices for our full home renovation in Alicante are €450/m² to €900/m², VAT not included; for houses and villas, €600/m² to €1,200/m². You can see the full breakdown on our renovation prices page.

Indicative schedule for a full flat renovation

For a 70 to 100 m² flat, the works break down into six phases: demolition, services and masonry, wall and floor finishes, joinery and ceilings, painting and final fittings, and snagging and handover; before those come the visit, the quote, the permits and the orders. The times for each phase are indicative and partly overlap.

Phase What happens Indicative duration
0. Before starting: visit, quote, permits, orders Technical visit within 48 to 72 hours, fixed itemised quote, declaración responsable or licence, choosing and ordering materials Several weeks before starting, depending on permits and lead times
1. Demolition and removal Protection of common areas, stripping bathrooms and kitchen, lifting floors and tiles, removing partitions, old joinery and services, rubble out 1 to 2 weeks
2. Services and masonry Chasing, new plumbing and drainage, new electrical installation, partitions, floor screeds, air conditioning pre-installation, door frames 3 to 4 weeks
3. Wall and floor finishes Tiling bathrooms and kitchen, flooring, plastering, waterproofing shower areas 2 to 3 weeks
4. Joinery, ceilings and fittings Suspended ceilings, doors, wardrobes, kitchen installation, switches and sockets, sanitaryware and taps 1 to 2 weeks
5. Painting and final fittings Painting walls and ceilings, skirting, shower screens, lighting, air conditioning 1 to 2 weeks
6. Snagging, cleaning and handover Touch-ups, final clean, testing services, installer certificates, handover with written guarantee A few days
Total on site 8 to 14 weeks

For a house or villa the scheme is the same, but roof, facade, exteriors and pool if there is one are added, plus a project and major works licence phase when the works require it. Hence the 3 to 6 months. Our villa renovation in Alicante page covers the specifics.

Phase 0: what happens before the works start

Before the first wall comes down there are between two and six weeks of work you do not see: visit, quote, permits, choosing materials and placing orders. It is the phase that most influences whether the works finish on time. A job that starts without materials decided and ordered stops halfway.

  • Technical visit. We do it within 48 to 72 hours in Alicante and within a 45 km radius. We measure, check walls, drainage stacks, the consumer unit, the condition of services and any damp. In older flats, we sometimes make exploratory openings. If you are abroad, we can do it with your key holder or agent and send you the findings.
  • Fixed, itemised quote. Free and with no obligation. It is the basis of the schedule: each item has its time. If you are not sure how to read a Spanish quote, see our guide on how to read and compare a Spanish renovation quote.
  • Permits. Most full renovations with no structural impact go through a declaración responsable, which allows a start from the day of filing; if there is a load-bearing wall or facade involved, a project and major works licence are needed, with a processing time we do not control. We handle the declaración responsable or licence with the town hall. If your building has a community of owners, the works must also be notified and, if common elements are affected, an agreement obtained.
  • Choosing and ordering materials. The things that take longest to arrive: kitchen units, windows, doors, imported porcelain tiles, made-to-measure shower screens. Ideally everything is chosen and ordered before starting, with delivery dates coordinated with the schedule. We work from samples, photos and video calls for owners who cannot visit showrooms in person.

Phases 1 and 2: demolition, services and masonry

Demolition takes one to two weeks and the services and masonry phase three to four: together they are almost half the works and where the surprises appear. It is the least glamorous part, but the one that determines whether the renovation lasts twenty years or causes problems in two.

In demolition, common areas are protected, bathrooms and kitchen are stripped, floors and tiles lifted, partitions and joinery removed and rubble taken out. In buildings with a community, the pace is set by noise hours and how rubble is taken down (protected lift, stairs or chute); our guide on community of owners permission for renovations explains the rules.

In services and masonry, walls are chased, the new water supply and waste network is run, new cabling and the consumer unit are installed, partitions are built, floors are screeded and air conditioning pre-installation is left in place. In 1960s to 1980s flats in Alicante this is the phase where lead or iron pipes, aluminium wiring, asbestos cement drainage stacks in poor condition or hidden damp usually appear. Replacing all of that is the right decision, and the quote should already allow for it, as we explain in the guide on renovating an old flat in Spain.

This phase also concentrates the drying times, which cannot be accelerated: a mortar screed needs days before flooring goes down; plaster must dry before painting; shower waterproofing has its curing time. A schedule that ignores them produces floors that lift and paint that cracks.

Phases 3 to 6: finishes, joinery, painting and handover

Wall and floor finishes, joinery, painting and snagging take five to nine weeks in total and are the phases in which the flat starts to look finished; the risk here is impatience and last-minute changes. The order matters: each trade prepares the ground for the next.

  • Wall and floor finishes (2 to 3 weeks). Tiling bathrooms and kitchen, flooring throughout, plastering. A 90 m² flat with large-format porcelain takes longer than one with standard format. If the existing floor is kept in part of the flat, it is shorter.
  • Joinery, ceilings and fittings (1 to 2 weeks). Plasterboard ceilings, doors, wardrobes, kitchen units, sanitaryware, taps and switches. This is the moment when a kitchen that arrives late brings half the site to a halt.
  • Painting and final fittings (1 to 2 weeks). Painting walls and ceilings, installing lighting, shower screens, air conditioning, skirting. Painting is done at the end so that it does not suffer from the other trades.
  • Snagging and handover (a few days). Touch-ups, cleaning, water and electrical tests, authorised installer certificates, handover of the documents and written guarantee of the works. For owners abroad we send a full photo and video record before you travel out.

Within a full renovation, the bathroom and the kitchen have their own sub-schedules: a bathroom renovation on its own takes 2 to 3 weeks and a kitchen 3 to 5 weeks. Integrated into the full job, they overlap with the rest. See the guide on how long a bathroom renovation takes for the detail.

What stretches a full renovation (and what you can control)

Renovations run late for five main reasons: surprises in older buildings, materials arriving late, changes during the works, unresolved permits and poor coordination of trades. Three of the five depend on planning and on the customer, not on the works themselves.

  1. Surprises in the building. A load-bearing wall where a partition was expected, a rotten shared drainage stack, rising damp on the ground floor, an uneven floor slab. In flats in the Centro, Carolinas, Benalúa, San Blas or Santa Cruz it is normal for something to appear. A thorough technical visit and a small margin in the schedule absorb it.
  2. Materials. A made-to-measure kitchen, PVC or aluminium windows, lacquered doors or a specific porcelain tile can have weeks of manufacturing lead time. If they are ordered when the works start instead of before, the site waits. And if they arrive broken or wrong, it waits again.
  3. Changes during the works. Moving a socket before the chase is closed takes minutes; moving it after tiling takes days. Every change of mind halfway through costs more time than it seems, and that is doubly true when decisions have to cross time zones.
  4. Permits. An unresolved major works licence or a pending community agreement prevents starting or stops the job. They must be processed before, not in parallel.
  5. Coordination of trades. If the electrician does not come when the builder has finished chasing, days are lost. A single project manager who plans the sequence and has the trades committed avoids gaps.

What you control: decide everything before starting, approve materials in good time, do not live in the flat during the works if possible, reply quickly when the project manager asks you something, and hire someone who gives you a phased schedule and not just an end date.

Alicante specifics: older flats, the coast and the heat

In Alicante there are three local factors that affect timescales: the age of the housing stock in the centre, the rules of communities in coastal buildings and the summer heat. None prevents renovating at any time of year, but they are worth considering when planning.

The 1960s to 1980s flats in the Centro, the Ensanche, Carolinas, Benalúa, San Blas or Pla del Bon Repòs almost always need complete new services and, frequently, damp treatment. That puts the works at the upper end of the 8 to 14 week range. The 1980s and 1990s apartments in Playa de San Juan, Albufereta or Cabo de las Huertas usually have better structure but aluminium windows without thermal break and small bathrooms, and communities sometimes limit working hours or the summer months, which means planning out of season. In the urbanisations of El Campello, Mutxamel, San Vicente or Sant Joan, villas add exteriors and roof, and a major works licence when there is an extension.

The heat of July and August does not prevent interior work, but it slows some tasks and complicates those that need open windows, such as painting and sanding. The heavy autumn rains do affect roofs, terraces and waterproofing; if your renovation includes them, bring them forward or push them back relative to those weeks.

Common mistakes

  • Choosing the company with the shortest timescale. An unrealistic timescale is paid for in drying times not respected, overlapping trades without control and endless snagging. Ask for a phased schedule, not a date.
  • Starting without the kitchen and windows ordered. They are the materials with the longest lead times. Ordered late, the works stop in phase 4.
  • Changing the layout or materials halfway through. Every change after services are closed or tiling is done costs days and money.
  • Not allowing for surprises in an older flat. If the quote and schedule do not include complete replacement of services, the surprise arrives in week two.
  • Living in the flat during a full renovation. It forces phased working, doubles protection and cleaning and stretches the timescale considerably.
  • Leaving permits to the last minute. A pending community agreement or licence stops the works at the worst moment.
  • Not fixing the timescale and how delays are handled in the contract. A written timescale with phases and the conditions for changes protects both sides.
  • Confusing "end of works" with "end of snagging". Handover includes touch-ups, cleaning, testing and documents. Ask what the company counts as handover.

When to call a professional

A full renovation is not a project to do in pieces with different self-employed trades coordinated by you, unless you have a great deal of experience and are on site every day: the timescale depends on the trades following each other without gaps, and that requires a project manager who plans, buys and resolves surprises daily. What you can do yourself is the decision-making: layout, materials, quality levels, and do it before starting.

There are also jobs that only qualified professionals can do: the new electrical installation and its certificate, the gas installation, and, when structure or facade is involved, the project and site supervision by a technician.

At Costa Renova we work with a single project manager from start to finish, a fixed itemised quote, handling of the declaración responsable or licence with the town hall and a written guarantee of the works, with photo and video updates for owners who are not in Spain. If you are planning the full renovation of your flat or house in Alicante or nearby, book the free technical visit: we give you a fixed quote and a realistic phased schedule, with no obligation. You can request it from our full home renovation in Alicante page or from the contact page.

Frequently asked questions

How long does a full renovation of a flat take?

Between 8 and 14 weeks on site for a flat of 70 to 100 m², according to our indicative timescales. A smaller flat with fewer items can be close to 8 weeks; a 100 m² flat with complete new services, a new layout and high-end finishes is closer to 14. Add the weeks beforehand for the quote, the paperwork and ordering.

How long does a villa renovation take in Spain?

Between 3 and 6 months, according to our indicative timescales. Houses add floor area, exteriors, roof, facade and often complete new services, and they frequently need a project and a major works licence, with processing time before anything can start.

How long from asking for a quote to the works starting?

It depends mainly on permits and materials. We do the technical visit within 48 to 72 hours in Alicante and the surrounding area; the fixed itemised quote follows the visit; the municipal procedure and ordering materials with lead times (kitchen, windows, doors, porcelain tiles) are what set the real start date. Allow several weeks between signing and starting.

Can I live in the flat during a full renovation?

It is not advisable. A full renovation means cutting water and electricity, demolishing bathrooms and kitchen and lifting floors, so the home is not habitable for most of the works. If you have no alternative, it can be organised in phases, but the total timescale stretches and the cost usually rises.

Which phase of a renovation takes longest?

Services and masonry, because it includes chasing walls, new pipes and cabling, partitions, floor screeds and preparing every surface. It usually takes a third of the works. The finishes (tiling, flooring, painting, joinery) look more visible, but they depend on that phase being done properly and dry.

Why do renovations run late?

The most frequent causes are surprises when demolishing in older flats (walls, hidden services, damp), materials arriving late or damaged, customer changes during the works, and unresolved permits or community approvals. A thorough technical visit, choosing materials before starting and a single project manager remove most of them.

Can a full renovation be shortened?

Up to a point. What really shortens it is having everything decided and ordered before starting, changing nothing during the works and not living in the flat. What cannot be accelerated are drying and curing times (screeds, plaster, waterproofing) or the manufacturing lead times for kitchens, windows or doors.

What time of year is best to renovate in Alicante?

Any time works for interior jobs. In summer the heat makes some tasks harder and in coastal buildings communities sometimes restrict works in high season; in holiday apartments the norm is to renovate between seasons. For roofs, facades and waterproofing, avoid the weeks of heavy autumn rain.

Updated: