What preparing the home means and how long it takes
Preparing your home before a renovation means leaving the work areas empty and accessible, protecting what stays, notifying the right people and documenting the starting condition; it takes a week for a bathroom or kitchen and two or three weeks for a full renovation. It is not a minor formality: a job that starts in a prepared home moves forward from day one, and one that starts with furniture half moved loses days and causes friction.
This guide is a practical checklist, in time order, written for homes in Alicante and the surrounding area: 1960s to 1980s flats in the centre and Carolinas, coastal apartments in Playa de San Juan or El Campello, villas on urbanisations in San Vicente or Mutxamel. It works whether you will live in the home during the work, move out temporarily, or, as many of our British and Irish clients do, prepare everything on one trip and manage the rest from home.
We assume you already have a fixed quote, a date and, if needed, the municipal paperwork filed. If not, start with the guide on how to read and compare a Spanish renovation quote.
Preparation calendar: what to do and when
Preparation falls into three moments: three weeks before (decisions and notifications), one week before (emptying and protection) and the day before (keys, photos and a walk-through). This table summarises the tasks by type of renovation.
| When | Bathroom or kitchen renovation | Full renovation |
|---|---|---|
| 3 weeks before | Confirm the date and order of work; notify the community | Decide whether you live in or move out; book storage; notify the community; apply for the skip permit if you are handling it |
| 2 weeks before | Choose and confirm materials with delivery dates | Confirm materials and lead times; speak to adjoining neighbours; arrange children, pets and working from home |
| 1 week before | Empty the room and the walkway; protect the rest | Empty the home or the first-phase areas; protect what stays; take down light fittings, curtains, pictures |
| 2 to 3 days before | Seal doors and ducts; leave a temporary bathroom or kitchen working | Seal clean zones; set up the living zone if you are staying |
| Day before | Hand over keys, locate stopcocks and consumer unit, photos of the starting condition | Keys, stopcocks, consumer unit, photos of the home and common areas, walk-through with the site manager |
The timescales of the work itself are in the quote: a bath to shower conversion takes 1 to 2 days, a bathroom renovation 2 to 3 weeks, a kitchen 3 to 5 weeks and a full flat renovation 8 to 14 weeks (70 to 100 m² flat). The longer the job, the more preparation matters.
Step by step to prepare the home
There are seven steps: confirm scope and schedule, empty and protect, seal against dust, notify the community, arrange keys and utilities, sort out children, pets and work, and photograph the starting condition. We take them one by one.
1. Confirm the scope and schedule with the company
Before moving anything, go through with the site manager which rooms are affected, in what order, and what must be empty on day one. In a full renovation not everything is emptied at once: sometimes the bathrooms and kitchen go first and the living room is used as temporary storage. Also ask how materials will come in and rubble go out (lift, stairs, a chute from a window on lower floors) and whether a skip or bags are needed. If the skip goes on the street, read the guide on skip hire and rubble removal in Spain.
2. Empty the work areas and protect the rest
Take everything you can out of the work areas: furniture, curtains, light fittings, pictures, rugs, plants, small appliances. Whatever stays in the rest of the home, group it and cover it with builder's plastic sheeting held down with masking tape. For a full renovation, consider a storage unit: in Alicante there are self-storage units rented by the month and it usually beats moving furniture from room to room as the job advances.
Use the moment to get rid of what is not coming back: the town halls of Alicante, Elche, San Vicente and Sant Joan have bulky-waste collection by appointment and recycling centres (ecoparques). This is the best time to do it, not once the job is under way.
If you want to take on dismantling kitchen units or wardrobes yourself to save money, first agree how appliances, water and gas will be disconnected; the limits are set out in the renovation guides and, for anything involving gas or electricity, by law.
3. Seal against dust
Demolition dust is very fine, gets everywhere and lingers for weeks. To reduce it:
- Close the doors of rooms not being worked on with plastic sheeting and tape from the outside, or with zipped dust-screen doors if you will be going in and out.
- Cover ventilation grilles and, above all, the indoor air conditioning units and their grilles: dust in the evaporator shortens the life of the machine.
- Protect the floor of the walkway with cardboard or builder's blankets over the plastic, so it does not tear under wheelbarrows.
- Cover the washing machine, fridge and any appliances that stay.
- Remove or cover clothes in wardrobes near the work.
The company protects too, but what you do before the first operative walks in always protects more.
4. Notify the community and the neighbours
Notify the work in writing to the president or the administrador, with approximate dates, working hours, the company's name and what will be done. If the work affects common elements (facade, external windows, soil stacks, terrace), you need the meeting's agreement: the guide on community of owners permission for renovations in Spain explains when and how.
Also speak in person to the neighbours above, below and either side. Advance notice and a "if there is any problem, tell me" avoid most complaints. If your Spanish is limited, a short written note in both languages works well. Ask about house rules: working hours, use of the lift for materials (in many coastal buildings, such as Albufereta or Playa de San Juan, it is prohibited or restricted), where the skip can go.
5. Arrange keys, utilities and access
Hand a set of keys to the site manager against a signed receipt. Show where the main water stopcock is, the stopcocks for each room, the consumer unit and, if there is one, the gas valve. Confirm that electricity and water will be live for the whole job: the work needs them. If the property is a recently bought resale and the supplies have been disconnected, arrange the reconnection in advance, and remember that a new or modified electrical installation needs the authorised installer's certificate (the boletín) before the supply company will connect it.
If there is a garage, agree whether the operatives can park or unload. If there is an entryphone, an alarm or an electronic lock, leave instructions. If you are abroad, the key handover usually goes through your key holder or agent, and the receipt protects both of you.
6. Sort out children, pets and working from home
During demolition, tile removal and chasing, the noise and dust make it hard to live in the home, and it is unsafe for small children and animals: open doors, tools, rubble. Ideally those stages coincide with days away. If you stay, set aside a sealed room away from the work as a clean zone, agree the hours of maximum noise and, if you work from home, accept that there will be days when you cannot.
With pets, especially cats, leaving the home during the noisy stage is the safest option. If that is not possible: a closed room, a sign on the door for the operatives and a check before opening the front door.
7. Photograph the starting condition
Take photos and, if you can, a video of every room before anyone comes in, and also of the common areas the work will pass through: entrance hall, stairs, lift, landing, courtyard. Photograph in detail any existing damage (a scratch in the lift, a broken tile in the hall). Share them with the company on day one; we take our own and then both sides have the same reference. Those photos settle any question at the end with the community, with a neighbour or with the insurer.
Preparation by type of home in Alicante
An old flat in the centre, a coastal apartment and a villa on an urbanisation are prepared differently: the access, the community rules and what needs protecting all change. Three common cases.
1960s to 1980s flats in the centre, Carolinas, Benalúa or San Blas
Buildings with narrow stairs, small or no lifts and, often, communities with strict rules on hours. Expect rubble to go down by hand or in bags, large items (shower trays, doors, kitchen units) possibly not fitting in the lift, and the light well to be the neighbour most sensitive to dust. If there are elderly neighbours, the personal notice matters even more. In these flats it is also worth keeping the guide on renovating an old flat in Spain: where to start to hand, because surprises tend to appear once things are opened up.
Coastal apartments in Playa de San Juan, Albufereta, El Campello or Santa Pola
Large communities with an administrador, seasonal rules (many prohibit works in July and August) and restrictions on using the lift. If the property is a holiday home, preparation is done in a single visit: empty it, turn off the water, leave keys and photos, and agree with the company a schedule of progress photos. This is the usual pattern for owners who live abroad, and it works. Salt air and humidity mean appliances and textiles that stay need particular protection.
Villas and houses in San Vicente, Mutxamel, Busot or coastal urbanisations
More space to store furniture (a garage or a closed room), a skip on the plot itself with no street permit needed, less conflict with neighbours. In return, the garden and the pool have to be protected from dust and from materials passing through, vehicle access decided and, if there is an irrigation system or an outdoor heat pump unit, these marked. If the work coincides with autumn, check terrace drains and gullies before starting: a heavy autumn storm with a job open is a bad combination.
Common mistakes
- Emptying halfway. Leaving "just one wardrobe" in the work room means moving it every day and it ends up full of dust and knocked about.
- Not sealing the air conditioning. Dust in the indoor units is a breakdown in the medium term; they are covered in five minutes.
- Notifying the community on the day the job starts. House rules, the lift and the hours are negotiated beforehand, not with the skip already at the door.
- Forgetting the storage unit. Moving furniture from room to room for 10 weeks wears you out, slows the job and damages the furniture. Storage for a few months is usually cheaper.
- Buying materials without confirming delivery dates. A shower tray that arrives two weeks late holds up the whole job. Confirm lead times before the start date.
- Not photographing the common areas. It is what causes most arguments at the end: a scratch in the lift that nobody knows the date of.
- Leaving valuables in the home without thinking. Not out of distrust, but out of order: a job has a lot of people coming and going. Keep jewellery, documents and cash away from the work areas, or take them with you if you are leaving the country.
- Not deciding what to do with children and pets. Improvising on demolition day is the most stressful moment of the whole job.
When to call a professional
Everything described in this guide you can do yourself, and it is the part of the renovation where your work saves most and risks least. What you should not take on is disconnecting services (gas, electricity, air conditioning) to dismantle units or appliances, or moving anything that affects common elements. That is what the company is for.
There are three situations where preparation gets complicated and deserves a prior visit:
- You do not know which rooms to empty or in what order because the job is large or will be done in phases while you live in the home. We plan it with you on the technical visit.
- The community objects to the skip, the hours or the lift. Our site manager speaks to the administrador and proposes alternatives (bags, hours, protection of common areas).
- The property is closed up or you live abroad, very common in coastal apartments. We organise collecting the keys, the starting-condition photos and the progress updates so you do not have to be there.
At Costa Renova we work with a single site manager from start to finish, who tells you in advance what needs to be empty, how materials will come in and how we will protect what stays. If you are about to start a full home renovation in Alicante or a bathroom renovation, ask for the free technical visit: we give you a fixed itemised quote and a preparation plan for your home, without obligation, through the contact page.
Frequently asked questions
What do I need to do before a renovation starts?
Empty the work areas, protect the rest against dust, notify the community and the neighbours, hand over keys, check the utilities, decide where children and pets will be, and photograph the starting condition of the home and the common areas. A week's notice is enough for a bathroom; for a full renovation, start two or three weeks ahead.
Do I have to empty the whole flat for a renovation?
Only for a full renovation with new floors and services throughout. For a bathroom, a kitchen or a partial renovation, it is enough to empty those rooms and the walkway, and protect the rest. Putting furniture in a rented storage unit or with family usually works out cheaper than shifting it from room to room during the job.
How do I protect furniture from building dust?
Group the furniture in the middle of the room or against one wall, cover it with builder's plastic sheeting and seal the edges with masking tape. Seal the room door with plastic. Demolition dust is very fine and gets through any gap, so two layers are worth more than good intentions.
Do I have to tell the community of owners before a renovation in Spain?
Yes, it is always advisable to notify the president or the administrador in writing, even if the work is internal and needs no authorisation. If it affects common elements (facade, terraces, soil stacks, external windows) you need the meeting's agreement under the Horizontal Property Law. Many communities also have rules on working hours and on using the lift for rubble.
What do I do with my pet during the renovation?
During demolition and dusty stages, it is best that they are not in the home: noise, dust and open doors are a real risk, especially for cats. If that is not possible, set aside a sealed room away from the work, off limits to the operatives, and take them out during the noisiest hours.
Do the water and electricity need to be cut off during the work?
Not in general: the job needs power and water to proceed. They are cut at specific moments (connections, changing the consumer unit, stopcocks) and the company tells you beforehand. What matters is that the supplies are live and the company knows where the stopcocks and the consumer unit are.
Why take photos before the renovation?
Because they are the proof of the starting condition of your home and of the common areas (entrance hall, lift, stairs). If there is damage at the end, the photos settle whether it was there before or came from the work. They also serve for the community of owners and the insurer. Share them with the company on day one; we take our own as well.