Renovation contract in Spain: what it must include

Guide · 10 min read · Costa Renova site team · updated

A renovation contract in Spain should include, at a minimum, the identity of both parties, the itemised quote as an annex, the start date and completion deadline, the schedule of payments by milestones, how changes and unforeseen problems are handled, penalties for delay, the written guarantee and the method of handover. It need not be long and it need not be drafted by a lawyer: it needs to be clear. We explain each clause and what it should say.

  • Fixed, itemised quote, free and with no obligation
  • Site visit within 48–72 h in Alicante and 45 km around
  • One project manager from start to finish
Illustrative image: renovation project plans
Illustrative image: renovation project plans.
On this page
  1. What the contract is for and what form it should take
  2. Table: clauses a renovation contract should include
  3. Line items, price and scope: the annex that holds everything up
  4. Deadlines, payment by milestones and penalties
  5. Changes, unforeseen problems and handover
  6. Insurance, licences and guarantee
  7. Specifics in Alicante and on the Costa Blanca
  8. Common mistakes
  9. When to call a professional

What the contract is for and what form it should take

A renovation contract puts in writing what will be done, for how much, by when, how it is paid, what happens if something changes or runs late and what guarantee remains at the end; it can be a separate document or the detailed quote itself signed by both parties with those clauses added. What matters is not the length, but that it answers those questions without ambiguity.

In a home renovation, the arguments are almost never about what is written down, but about what is not: whether the final clean was included, whether replacing the soil stack was an extra, when payment was due, how long the guarantee lasts. A clear contract does not prevent surprises (in a 1970s flat in the centre of Alicante there is always one), but it does stop every surprise becoming a dispute.

For British and Irish owners there is an added point: the contract will almost certainly be in Spanish, and Spanish contracts for small works are typically shorter and less formal than a UK building contract. That is not in itself a warning sign, as long as the essentials are there. Ask for a bilingual version if the company can provide one, or have your gestor or solicitor read through it; do not sign a document you cannot read.

This guide speaks in general terms about what a contract between a private individual and a renovation company should contain. It is not legal advice: for large jobs, jobs with an architect's project or high sums, having a lawyer or the architect review it is money well spent. For a bathroom or flat renovation, what follows is enough to sign with peace of mind.

Table: clauses a renovation contract should include

Twelve sections cover the essentials of a renovation contract; the first five are indispensable and the rest avoid most disputes. Use it as a checklist before signing.

Clause What it should say Indispensable
Parties Client's and company's details (registered name, NIF, address, person in charge) Yes
Subject and quote Description of the work and the itemised quote as a signed annex Yes
Price and VAT Total amount, applicable VAT rate, what is excluded Yes
Deadlines Start date, execution period, conditions it depends on Yes
Payments Schedule by milestones, amount of each, method of payment, invoicing Yes
Changes and unforeseen problems Procedure: written pricing, approval, annex Highly advisable
Delays and penalties Causes not attributable, penalty per day, cap Highly advisable
Insurance and staff Public liability insurance in force, registered workers, subcontractors Highly advisable
Licences and paperwork Who files, who pays fees, work does not start without the filing Highly advisable
Guarantee Scope, duration, how to claim, materials guarantee Yes
Handover Joint inspection, snagging list, time to resolve, signed handover certificate Highly advisable
Termination and disputes Grounds for termination, settlement, route for claims Advisable

If the document you are given lacks those marked "Yes", ask for them to be added. If the company refuses, read the guide on how to choose a builder in Spain and the red flags.

Line items, price and scope: the annex that holds everything up

The heart of the contract is the itemised quote, signed as an annex: it defines what is done, to what grade, in what quantity and at what price, and marks out what is excluded. Without a detailed annex, the other clauses have nothing to apply to.

What that annex should contain:

  • Line items with unit, quantity and unit price: demolition, masonry, plumbing, electrics, air conditioning, tiling and flooring, joinery, plasterboard, painting, cleaning.
  • Grades and references of materials: format and range of floors, type of sanitaryware and taps, internal doors, electrical fittings. If the client chooses and buys materials, state who supplies them and what happens if they arrive late or damaged.
  • Express exclusions: what is not included (for example, kitchen units if the client buys them, painting if the client does it, municipal fees).
  • Ancillary work: waste management, skip and bags, protection of common areas, final clean.
  • Total price and applicable VAT. Renovation of a private home may be charged at the reduced 10% VAT rate if conditions are met (home more than two years old and materials below 40% of the taxable base); the contract should state the rate applied and that, if the conditions are not met, the general rate applies.

As an order of magnitude to check the annex is coherent: a full flat renovation costs €450 to €900 per m², VAT not included; a complete bathroom €5,500 to €12,000, VAT not included; a kitchen €7,000 to €18,000, VAT not included. The guide on how to read and compare a Spanish renovation quote explains how to review it line by line.

Deadlines, payment by milestones and penalties

The contract should set a start date, an execution period and what it depends on, a payment schedule tied to milestones of completed work and a reasonable penalty for delay attributable to the company, with a cap. These are the three clauses that avoid the most disputes.

Deadlines

State a start date (or an event that fixes it: "X days after the declaración responsable is filed") and an execution period. Our reference timescales are 1 to 2 days for a bath to shower conversion, 2 to 3 weeks for a bathroom renovation, 3 to 5 weeks for a kitchen and 8 to 14 weeks for a full renovation of a 70 to 100 m² flat. The contract should also say what conditions the deadline: confirmation of materials by the client, licences, access to the property. The guide on how long a full renovation takes shows what it depends on.

Payment by milestones

A typical schedule for a full renovation:

  1. Initial payment on signing, for materials and start-up.
  2. Payment on completion of demolition and services.
  3. Payment on completion of tiling, flooring and plasterboard.
  4. Payment on completion of joinery and kitchen.
  5. Final payment on handover, after the joint inspection and snagging.

For a bathroom, two or three milestones are enough. The essential thing is that each payment is defined by a verifiable event, that the company issues an invoice for each one and that the final payment is significant: it is your guarantee that the finishing details get done. A contract that asks for most of the money before starting is a contract you should not sign. If you are paying from a bank abroad, write the milestones into your own calendar so transfers go out on time.

Penalties for delay

A balanced clause distinguishes delays attributable to the company (lack of staff, poor planning) from those that are not (client-supplied materials arriving late, changes of scope, hidden problems, a municipal decision pending) and sets a penalty per day of attributable delay, with a cap on the total. The aim is not to punish but to make the deadline mean something. By symmetry, some contracts provide for interest or suspension of work if the client does not pay.

Changes, unforeseen problems and handover

The contract should say how changes requested by the client and problems found on opening up are handled: priced in writing, approved before execution and annexed to the contract; and how the work is handed over: joint inspection, snagging list with a deadline and a signed certificate. This is where "extras" and "we will sort that out later" are decided.

Client changes

Changing a chosen floor, adding a light point, moving a radiator: these are common and legitimate changes. The correct procedure is for the company to price them in writing (cost and effect on the deadline), the client to approve them and for them to be added to the quote. Without a procedure, changes pile up verbally and appear on the last invoice as a surprise. For an owner abroad, approving by email creates exactly the paper trail you want.

Hidden problems

In older flats in Alicante they appear when things are opened up: a load-bearing wall where a partition was expected, an asbestos-cement soil stack, wiring with no earth, a floor slab in poor condition under the bathroom. The contract should establish that the company documents them (photos, description), prices them in writing and does not proceed until approved, except for urgent safety work. What should not happen is a problem being resolved without notice and charged for afterwards.

Handover

At the end, a joint inspection room by room, a snagging list (visible defects: paint, silicone, doors that catch, switches) with a deadline to resolve them, and a signed handover certificate that fixes the date from which the guarantee runs. The final payment is tied to that handover. If the company hands over without a joint inspection and asks for the last payment "now", you are not receiving the work: it is being left with you. If you cannot be in Spain for the handover, the contract can provide for it to be done by someone you delegate, or on a final visit, with a full set of photographs beforehand.

Insurance, licences and guarantee

The contract should record that the company has public liability insurance in force and registered workers, who files the licence or declaración responsable and who pays the fees, and the written guarantee on the work with its scope and duration. Three short clauses that protect you against the most serious problems.

Public liability insurance and staff

State that the company holds public liability insurance covering damage to the home, to neighbours and to third parties, and that staff (own or subcontracted) are registered. Ask for a copy of the insurance certificate as an annex. It is not distrust: it is what covers you if the work causes a leak into the flat below or damage to the communal lift.

Licences and paperwork

Who prepares and files the declaración responsable or minor works licence with the town hall (in our case, we do it as part of the service), who pays the fees and the construction tax (normally the owner, under the ordinance) and that the work does not start until the filing is made. If the work affects common elements, state that the client provides the community's authorisation. The guide on the declaración responsable for building works in Spain explains the procedure.

Guarantee

The written guarantee on the work should say what it covers (workmanship, services, watertightness of bathrooms, finishes), how long it lasts, from when it runs (the handover), how to claim and how it fits with each manufacturer's guarantee on materials. At Costa Renova a written guarantee on the work is one of our commitments. Independently of the contract there are the legal liabilities for building work, which in general apply to jobs with an architect's project.

Specifics in Alicante and on the Costa Blanca

There are three local situations worth reflecting in the contract: renovating a coastal apartment at a distance, the rules of the community of owners and the usual hidden problems of older buildings. They are not different clauses, but they are nuances.

  • Renovation at a distance: owners who live abroad and renovate in Playa de San Juan, Torrevieja, Benidorm or Santa Pola. The contract should include the follow-up system (photos or video of progress at each milestone), key management and the handover of the work, which can be done on a final visit or by delegation. Payment milestones tied to progress photos work well, and an English-speaking point of contact named in the contract removes most of the friction.
  • Community of owners: working hours, use of the lift, protection of common areas, skip or bags. The contract should record that the company will comply with the house rules the client provides and will protect the common areas, with photos of the starting condition.
  • 1960s to 1980s buildings: expressly include the procedure for hidden problems and, if the structure is known to be doubtful, provide for test openings before the final quote is fixed.
  • Season: in coastal apartments, many communities do not allow works in summer. The contract deadline must take that into account.

Common mistakes

  • Signing only the quote, with no deadlines, payments or guarantee. A quote is a price offer, not a complete agreement. Add the clauses or sign a separate contract.
  • Accepting a payment schedule that front-loads most of the money. The money should follow the completed work.
  • Leaving changes "verbal". It is the main cause of final arguments over extras. Every change in writing and approved beforehand.
  • Not defining which materials the client supplies and what happens if they fail. A shower tray bought by the client that arrives broken or late stops the job and nobody knows who is responsible.
  • Not fixing the handover. Without a joint inspection and a snagging list, the job ends when the company stops turning up.
  • A guarantee with no scope or duration. "Full guarantee" means nothing; "X years on services and workmanship, from handover, in writing" does.
  • Not asking for the liability insurance as an annex. It is forgotten until the downstairs neighbour calls about a stain on the ceiling.
  • Signing in a hurry to "reserve a date". A contract is read calmly; if they will not let you, that is a sign.
  • Signing a Spanish document you have not had translated or explained. You are bound by what it says, not by what you understood.

When to call a professional

A contract for a bathroom, kitchen or flat renovation you can review yourself with this guide; for jobs with an architect's project, structural changes, change of use, high sums or if you live abroad and are renovating at a distance, it is worth having a lawyer or the architect directing the work review it. The cost of that review is small compared with a dispute halfway through the job.

It is also worth taking advice when:

  • The company proposes a contract you do not understand or with clauses that seem one-sided (termination only in its favour, penalties only for you, payments without milestones).
  • The work involves the community of owners in common elements and the split of responsibilities between you, the community and the company is not clear.
  • There are several trades subcontracted to different companies and nobody takes on the coordination.

At Costa Renova the contract is the fixed, detailed, itemised quote, free and without obligation, with deadlines, payment by milestones, a procedure for changes, a written guarantee on the work and a single site manager from start to finish. Our price ranges are on the renovation prices page. If you are about to start a full home renovation in Alicante, ask for the free technical visit through the contact page and check our document against this guide: if something is missing, tell us.

Frequently asked questions

Is a written contract compulsory for a renovation in Spain?

There is no general legal obligation to put a home renovation between a private individual and a company in writing, but without a document you cannot prove what was agreed: not the line items, not the deadlines, not the price, not the guarantee. A detailed quote signed by both parties, with deadlines, payments and guarantee, already works as a contract. What is no use is a verbal agreement.

What should a renovation contract in Spain include?

The identity of the parties, a description of the work and the itemised quote as an annex, price and VAT, start date and deadline, payment schedule by milestones, handling of changes and unforeseen problems, penalties for delay, public liability insurance, licences and paperwork, written guarantee, handover of the work and dispute resolution. With those points you cover the essentials.

How are renovations paid for in Spain, up front or by milestones?

By milestones of completed work: a proportionate initial payment on signing to buy materials, interim payments on completing stages and a final payment on handover, after inspecting the work. Each milestone should be defined in the contract (for example, completion of services, completion of tiling) so there is no argument about when payment is due.

What happens if the renovation runs late?

It depends on what the contract says. The usual approach is to set a deadline with some margin, define which causes of delay are not the company's fault (client-supplied materials arriving late, client changes, hidden problems) and a penalty per day of delay attributable to the company, with a cap. Without a clause, claiming for a delay is much harder.

How are changes during the work handled?

With a written procedure in the contract: any change of scope or grade is priced in writing (cost and effect on the deadline), the client approves it and it is added as an annex. That avoids the final argument over extras. Hidden problems (a load-bearing wall, a broken soil stack) are treated the same way: documented, priced and approved before being carried out.

What guarantee should appear in a renovation contract?

The guarantee the company gives on its work, in writing, with its scope (what it covers: workmanship, services, watertightness) and its duration, and a reference to the manufacturers' guarantees on materials. The legal liabilities for building work exist independently of the contract, but the contractual guarantee is the one you can enforce directly.

Can I cancel a renovation contract in Spain?

The contract should say how: in which cases each party may terminate (serious breach, abandonment of the work, non-payment), with what notice and how the work done to that point is settled. Without a clause, termination is possible but more contentious. If the work is abandoned, document the state with photographs and send a written demand before anything else.

Updated: