Converting a commercial unit into a home: the short answer
A commercial unit can be converted into a home if the municipal planning rules allow it, if the unit is capable of meeting the habitability conditions (usable floor area, clear ceiling height, natural ventilation and light in the rooms, bathroom and kitchen with their services) and if the community of owners' statutes do not prohibit it. With those three conditions met, you need an architect's project, a change-of-use licence from the town hall (generally as major works) and, on completion, the first occupation licence. The works cost €500 to €950 per m², VAT not included, and the project and licence from €1,500, plus municipal fees.
In Alicante there are many empty ground-floor commercial units (locales) on secondary streets in the Centro, Carolinas, San Blas, Benalúa, El Pla or Babel, and in Elche, San Vicente or Torrevieja, and the idea of turning them into homes is increasingly common, both to live in and to let. Foreign buyers see a cheap "local" on a portal and picture a ground-floor apartment. It is an operation that can go very well or very badly, and the difference lies in what is checked before buying or starting. This guide walks through the requirements in the order they should be looked at, the permits, the works and the costs, without regulatory figures that change over time: that is what the technician is for.
The three filters before anything else
Planning, habitability and the community: if any of the three fails, the project does not happen, however attractive the unit.
| Filter | What is checked | Where or who | If it fails |
|---|---|---|---|
| Planning | That the plan allows housing on that plot and floor; density limits; conditions in the bylaws for ground-floor homes | Town hall (planning department) or an architect's enquiry | No change of use is possible |
| Habitability | Minimum usable area, clear height, natural ventilation and light, bathroom, kitchen, services, accessibility | Architect, applying the Valencian Community's housing design and quality regulations | Sometimes fixed with works (lowering the floor, opening windows); sometimes not |
| Community | Statutes and constitutive deed; works on the facade or common elements | Administrator, horizontal division deed | A community meeting resolution is needed, which may not be obtained |
The honest approach is to pass all three filters with a feasibility study signed by an architect before buying or asking for works quotes. It costs little compared with what is at stake.
Filter 1: the planning rules
The town hall decides whether there can be a home on that plot and on that floor; it is not an automatic right of the unit's owner.
Each municipality has a general plan and bylaws that set the permitted uses in each zone. In many residential zones of Alicante, residential use is allowed on the ground floor, but with conditions (for example, on the relationship with the street, the height, the courtyards or the maximum number of homes per plot). In others, the plan reserves the ground floor for commercial uses, or the density is already used up in the building. There may also be conditions for protected buildings or old-town settings.
What is done: a planning enquiry to the relevant town hall (Alicante, Elche, Benidorm, San Vicente, Santa Pola, Torrevieja and so on) or an analysis of the plan by the architect. This step says "yes", "no" or "yes with conditions", and without it everything else is a waste of time.
Filter 2: habitability (floor area, height, ventilation, light)
The Valencian Community's housing design and quality regulations set what a home must have; the unit must be able to meet them through the works.
We do not give figures because they depend on the type of home and on updates to the rules; these are the points that decide:
Clear ceiling height
The most common reason a unit does not work. It is measured from finished floor to finished ceiling in the habitable rooms. A unit that "looks tall" loses centimetres when a new floor with insulation and services goes in and a suspended ceiling is added to run services and insulate. Mezzanines and units with low ceilings at the back are the ones that usually fail. Sometimes height is gained by lowering the floor, if the foundations and services allow it.
Natural ventilation and light
Every habitable room (living room, bedrooms, kitchen) needs openings onto a facade or a courtyard with minimum sizes in relation to its floor area. A long unit with a single shopfront onto the street and no courtyard can only have habitable rooms at the front; the back is left for bathroom, utility, hallway or storage. This shapes the layout and often the number of bedrooms. Existing light wells are a great ally, if the unit has access to them.
Usable floor area and minimum programme
The home must have a minimum usable area and a minimum programme: living space, kitchen, full bathroom, bedroom (or a studio in small homes), with minimum areas per room. In 40-50 m² units it takes careful design.
Services
Water, drainage (connected to the mains, and watch the level of the sewer on ground floors), electricity with adequate power, bathroom and kitchen ventilation to the outside, and, if a gas hob is fitted or extraction is needed, a flue, which usually requires community agreement.
Accessibility and safety
Access from the street, level changes and fire safety conditions (relationship with the rest of the building, entrance door) also come into the project.
Facade
Turning a shopfront into windows and a front door means working on the facade, which is a common element: the design must respect the look of the building and the bylaws, and go through the community.
Filter 3: the community of owners
If the statutes do not prohibit residential use in the commercial units, the change of use itself does not usually need authorisation, but works on the facade and common elements do.
The first thing is to read the building's constitutive deed and statutes: some communities' statutes reserve the units for commercial use or expressly prohibit using them as homes. In that case the statutes have to be amended, with the majority required by the Spanish horizontal property law, and it is realistic to expect that it may not be achieved.
If there is no prohibition, the owner can change the use, but works affecting common elements need the meeting's authorisation: opening or altering openings in the facade, installing a flue or chimney, connecting to the main soil stack, running services through common areas, opening a door onto the entrance hall. Your lawyer can obtain the statutes; the administrator (administrador de fincas) is the person to approach first.
A tip: presenting the community with a clear project (an elevation of the new facade, what is touched and what is not, the works programme, how rubble is managed) makes agreement much easier. We prepare that documentation with the architect.
Permits: project, change-of-use licence and first occupation
The change of use from commercial to residential is processed with an architect's project and a licence from the town hall, generally as major works, and on completion the first occupation licence is applied for.
| Phase | Document | Who | Who controls the timing |
|---|---|---|---|
| Feasibility | Feasibility report (planning, habitability, community) | Partner architect | Us and the technician |
| Project | Change-of-use and works project, including services | Partner architect | Us and the technician |
| Licence | Major works and change-of-use licence | Town hall | The town hall |
| Works | Execution with site supervision | Costa Renova and technicians | Us: 8-14 weeks for 50-80 m² |
| Completion | Final works certificate | Technicians | Us and the technician |
| Occupation | First occupation licence | Town hall | The town hall |
| Afterwards | Catastro, Land Registry, utilities, energy certificate | Owner with our help | Public bodies |
It is a major works process: it cannot be processed through a declaración responsable for minor works, because it changes the use of the property and, almost always, the facade. First occupation is essential: without it there is no home for the purposes of utilities, sale or letting; we go into it in the guide on the cédula de habitabilidad in Alicante.
We coordinate the whole project and licence process with partner architects, so that you have a single point of contact, in English, from feasibility to handover.
What it costs to convert a commercial unit into a home
The works cost €500 to €950 per m², VAT not included; the technical project and the change-of-use licence from €1,500; municipal fees extra.
| Item | Guide price (VAT not included) | Note |
|---|---|---|
| Conversion works | €500 to €950 per m² | Demolition, light structure, complete services, insulation, windows and doors, bathroom, kitchen, finishes |
| Technical project and change-of-use licence | From €1,500 | Partner architect: feasibility, project, site supervision, completion |
| Municipal fees | Set by the town hall | Not set by us |
| First occupation | Tied to the project | Final works certificate and submission |
| Energy certificate | €90 to €180 | Needed to sell or let |
| New facade (windows, door) | Within the works; windows €350 to €900 each | According to the design approved by the community |
A 60 m² unit comes to roughly €30,000 to €57,000 of works, plus project, licence and fees. What places the price at one end or the other: the state of the unit (whether the floor has to be lowered, damp treated, anything reinforced), how much facade is altered, the distance to the soil stacks and the supply connection, the quality of bathroom and kitchen, and whether aerotermia or splits are installed. The services generally start from scratch, which is an advantage: the resulting home is new inside. See our renovation prices page for the figures in context.
On VAT: the change-of-use works are usually charged at 21%, because the property is not a home when the works are contracted. The 10% rate is reserved for renovations of homes owned by private individuals and more than two years old. We check it in the quote. Our commercial renovation in Alicante page covers the works side in more detail.
The works: what is done and in what order
The conversion is a full renovation from scratch: the unit is stripped out, the floor, facade and services are resolved, and the home is built.
- Demolition and strip-out: suspended ceilings, partitions, the unit's old services, shopfront.
- Floor: rising damp treatment where needed (very common in Alicante ground floors; see rising damp in Spain), insulation, build-up with services, or lowering if height is short.
- Facade: closing the shopfront, new window and door openings according to the project approved by the community.
- Complete services: plumbing, drainage (watch the level), electrics with a new consumer unit, ventilation, climate control (aerotermia or splits), telecoms.
- Partitions and insulation: layout in plasterboard or brick, thermal and acoustic insulation on the facade, party walls and ceiling (there is usually a home above).
- Windows and doors, bathroom, kitchen, finishes: tiling, floors, paint, internal doors.
- Completion and first occupation.
On ground floors, acoustic insulation from the neighbour above and from the street is important and often underestimated. The finished home will need an energy certificate to sell or let; see the guide on the energy performance certificate in Spain.
Common mistakes
- Buying the unit before checking the planning rules. The most expensive mistake: if residential use is not permitted, no project can fix it.
- Relying on "there are other converted units on the street". Each plot and each building has its own conditions and density; what was done next door years ago may not be possible today.
- Not measuring the real clear height allowing for the new floor and suspended ceiling.
- Designing bedrooms at the back of the unit with no window. They will not be habitable rooms; the project will not pass.
- Ignoring the community statutes until the project is drawn up.
- Forgetting the drainage level. On ground floors the bathroom waste may end up below the sewer and need a pump.
- Quoting without treating the damp in the floor. Rising damp in ground-floor units is frequent; treating it after the works is very expensive.
- Counting on 10% VAT. It is normally 21%; running the numbers with the wrong rate throws the investment out.
- Starting the works without a licence. It is major works; without a licence it is stopped, fined and may not be regularisable.
When to call a professional
Converting a commercial unit into a home requires an architect from the feasibility stage, a major works licence and a company to carry out the works under technical supervision; there is no DIY version.
What you can do yourself at the start:
- Ask the administrator for the statutes and the constitutive deed, or find them in the deed; your lawyer can help.
- Measure the clear height and note where there are openings onto the facade or a courtyard.
- Ask the town hall, or ask us to enquire, whether residential use is permitted for that unit.
- Think about the home you need (number of bedrooms, own use or letting) to see whether it fits.
What is worth commissioning as early as possible is the feasibility study with an architect: in writing, with the three filters checked. With it you can negotiate the purchase knowing where you stand, or walk away from the unit having lost only the cost of the study.
At Costa Renova we check the feasibility of your unit in Alicante and up to 45 km away with partner architects, coordinate the project and the change-of-use licence, carry out the works with a single person responsible, and handle the first occupation and the energy certificate on completion. The first visit is free and the quote is fixed and itemised; if you are abroad, we work by email and video call. Start at commercial renovation in Alicante or get in touch through our contact page.
Frequently asked questions
Can any commercial unit be converted into a home in Spain?
No. The municipal planning rules must allow residential use in that zone and on that floor, the unit must be able to meet the habitability conditions (floor area, ceiling height, natural ventilation and light, bathroom, kitchen) and the community statutes must not prohibit the change. A prior feasibility study avoids buying a unit that can never become a home.
What minimum ceiling height does a unit need to become a home?
The habitability regulations of the Valencian Community require a minimum clear height in habitable rooms that is greater than many units with low suspended ceilings or mezzanines actually have. It is measured from finished floor to finished ceiling, allowing for the new floor build-up and the services. It is the first thing we check.
Do I need permission from the community of owners?
It depends on the statutes. If they do not expressly prohibit residential use in the commercial units, the change of use itself does not usually need authorisation, but works affecting the facade or common elements (new windows, drains, flues, extraction outlets) do. Check the statutes and speak to the administrator before starting.
What licence do I need to convert a commercial unit into a home?
A change-of-use licence from the town hall, with a project drawn up by an architect, which is generally processed as major works because the use is altered and often the facade too. On completion, with the final works certificate, the first occupation licence is applied for. We coordinate the project with partner architects and handle the procedures.
How much does it cost to convert a commercial unit into a home?
The works cost €500 to €950 per m², VAT not included, plus the technical project and change-of-use licence from €1,500, and municipal fees. A 60 m² unit comes to roughly €30,000 to €57,000 of works, plus project, licence and fees.
How long does it take?
Between feasibility, project, licence, works and first occupation, several months. The works themselves, for a 50-80 m² unit, are like a full renovation: 8 to 14 weeks. The licence timing depends on the town hall and is the part we do not control.
What about VAT?
The change-of-use works are usually charged at the general 21% VAT rate, because the property is not a home when the works are contracted. The reduced 10% rate applies to renovations of homes owned by private individuals and more than two years old; we check your case in the quote.
Can I sell or let it afterwards?
Yes. With the first occupation licence granted and the use updated at the Catastro and the Land Registry, the home is a home for all purposes. You will also need the energy certificate, which we also arrange.