# Restaurant and bar renovation cost in Alicante

Renovating a restaurant or bar in Alicante costs €600 to €1,200 per m², IVA not included, and the works take 4 to 10 weeks. That range covers the hospitality installations: kitchen, smoke extraction, air conditioning and toilets.


## How much does a restaurant or bar renovation cost?

**Hospitality has its own range: €600 to €1,200 per m², before IVA.** It is higher than for general retail (€300 to €800 per m²) because a bar or restaurant needs more installations, tougher ones and more regulated ones. For the whole service see [commercial renovation in Alicante](/en/commercial-renovation-alicante/), or the Spanish page on [bars, restaurants and hotels](/reformas-bares-restaurantes-hoteles-alicante/). If your unit is another type of business, the [commercial unit renovation cost](/en/prices/shop-and-commercial-unit-renovation-cost-alicante/) is the reference.

Examples of the sum (before IVA): 60 m² gives €36,000 to €72,000; 100 m² gives €60,000 to €120,000; 150 m² gives €90,000 to €180,000. These are multiplications of the range and do not replace a quote.

## What explains that price

**In hospitality, most of the cost is in what does not show in the photograph.** These are the items that concentrate the effort:

| Item | What it involves | Effect on cost |
|---|---|---|
| Smoke and grease extraction | Hood, duct to the roof, filters, ventilation | High; depends on the route and the building |
| Kitchen | Washable floors and walls, drainage, gas and water points | High |
| Air conditioning | Units for dining room and kitchen, with air renewal | Medium to high; splits from €900 to €1,600 installed |
| Toilets | Number, accessibility, plumbing | Medium |
| Electrics | Power, consumer unit, ambient lighting | Medium to high |
| Bar and made-to-measure furniture | Carpentry, worktops, finishes | Varies with quality level |

## Smoke extraction and ventilation

**The smoke outlet is usually the most delicate point of a restaurant project.** In a residential building, the duct route to the roof, the community of owners' consent and the noise of the extractors all shape the design. It is worth resolving before you commit to the lease: a visit beforehand tells you whether it is feasible and what it costs. Regular grease cleaning also becomes part of the maintenance afterwards.

## Kitchen, plumbing and toilets

**The kitchen and toilets drive the plumbing installation.** You need drainage, kitchen waste lines with a grease trap where appropriate, and enough hot water. See our [plumbers in Alicante](/en/plumber-alicante/) for this part. Toilets must also be sized and accessible according to what the project technician determines. We do not assume any particular regulation here, because it depends on the unit and the capacity.

## Air conditioning and comfort

**A full dining room and a working kitchen need properly sized air conditioning.** In Alicante, summer heat and doors left open onto a terrace complicate the choice of equipment. Look at [air conditioning in Alicante](/en/air-conditioning-alicante/) for the options of splits or ducted systems.

## Activity licence and works licence

**Opening or changing a bar or restaurant involves two different things: the works and the activity.** Interior works are in many cases processed through a declaración responsable or a licencia de obra menor, and with structural changes, through a project and a licencia de obra mayor. The activity (opening, capacity, fire safety, noise) has its own procedure and usually needs a technician. Our [guide to licences and opening a shop or bar in Alicante](/en/guides/business-licence-and-opening-a-shop-or-bar-in-alicante/) explains the order of steps, and the Spanish page [proyectos y licencias de obra](/proyectos-licencias-obra-alicante/) gives the basics.

## Timeline: 4 to 10 weeks

**A hospitality renovation takes 4 to 10 weeks.** The programme depends on the extraction, equipment delivery and the order of trades. In tourist areas such as Playa de San Juan, Benidorm or Santa Pola, scheduling the works outside the high season avoids losing sales.

## How we work: turnkey

**One project manager coordinates the whole process.** A technical visit within 48 to 72 hours, a fixed quote itemised by section, a programme, the works, and a handover with a written guarantee on the work. We handle the works licence or declaración responsable with the town hall. If you are an owner or investor based abroad, we report by photo and video and explain the paperwork in English.

## What to check before renting or buying the unit

**A technical visit before the contract avoids expensive surprises.** If you have not yet closed the lease or purchase, ask us to review these points:

- **A feasible smoke outlet:** a workable route to the roof, and whether the community can authorise it.
- **Previous use of the unit:** if it already had a hospitality activity, part of the installations may be reusable.
- **Contracted electrical power** and the state of the consumer unit; see [electricians in Alicante](/en/electrician-alicante/).
- **Clear height and space** for ceilings, ducting and equipment.
- **Position of toilets and drains** relative to the main sewer.
- **Access for deliveries** and waste handling.

With this you can negotiate the rent better, ask for a rent-free period or simply rule out a unit that would cost too much to adapt.

## How to avoid budget overruns

**A fixed quote protects you from both surprises and constant additions.** A hospitality job usually overruns for three reasons: hidden installations nobody saw, changes of mind halfway through and supply delays. Visiting the unit, opening inspection holes where necessary, defining the equipment before starting and signing changes in writing reduce all three. To learn more about comparing offers, read our guide on [how to read and compare a Spanish renovation quote](/en/guides/how-to-read-and-compare-a-spanish-renovation-quote/).

## Ask for your quote

**The visit is free and without obligation.** Tell us what type of unit it is and how many square metres it has, and we will prepare a fixed quote. Request it through the [contact page](/en/contact/).