To renovate an old flat from the 1960s to 1980s in Alicante you start with what you cannot see: water and electrical services, the condition of drainage stacks and walls, damp and windows. A full renovation costs €450/m² to €900/m², VAT not included, and takes 8 to 14 weeks for a 70 to 100 m² flat. This guide explains what to check first, in what order to do the works and which mistakes to avoid, whether you have just bought or have owned the flat for years.


## Where to start when renovating an old flat

**Renovating an old flat starts with diagnosing what you cannot see: the electrical installation, water and waste pipes, drainage stacks, load-bearing walls, damp and windows. With that diagnosis the scope is decided and the quote prepared; the works then always follow the same order: demolition, services, masonry, finishes, joinery and painting.** Starting by choosing the tiles is the surest way to watch the budget run away later.

Many British and Irish buyers on the Costa Blanca end up with exactly this kind of property: a well-located flat at a good price that has not been touched since it was built. In Alicante, "old flat" usually means a 1960s, 1970s or 1980s flat in the Centro, the Ensanche-Diputación, Carolinas, Benalúa, San Blas, Pla del Bon Repòs, Garbinet or Santa Cruz, or a 1970s or 1980s apartment in Playa de San Juan, Albufereta or El Campello. They share several traits: original or patched services, aluminium windows without thermal break, terrazzo floors, layouts with a closed kitchen and a long corridor and, near the sea, salt damage and damp. They are flats with good structure and good ceiling heights that deserve a renovation, provided it is done in the right order.

A full renovation of these flats costs, according to our indicative prices, €450/m² to €900/m², VAT not included, and takes 8 to 14 weeks for 70 to 100 m². You have the details of the service and prices on our [full home renovation in Alicante](/en/full-home-renovation-alicante/) page.

## What to check before deciding anything: the diagnosis list

**Before quoting an old flat, eight points have to be checked: consumer unit and electrical installation, water network, waste and drainage stacks, damp, walls and structure, windows and insulation, floors and ceilings, and the condition of the common areas and the community rules.** What you find at each one defines the scope and the cost.

| What to check | What usually appears in 1960s to 1980s flats | What it means for the renovation |
|---|---|---|
| Electrical installation | No earth, few circuits, old cabling, sometimes aluminium, fuse board | Complete new installation with consumer unit, RCDs and separate circuits; installer certificate |
| Water network | Lead or galvanised iron pipes, low pressure, leaks | Complete replacement with cross-linked polyethylene or multilayer pipe |
| Waste and drainage stacks | Lead or iron wastes, asbestos cement stacks, insufficient falls | New PVC wastes; shared stack to be agreed with the community |
| Damp | Rising damp on ground floors, condensation and mould in bedrooms, salt damage near the sea, leaks from terraces | Diagnosis and treatment before finishing |
| Walls and structure | Solid brick load-bearing walls mixed with columns, old props | Check before changing the layout; project and major works licence if a load-bearing wall is opened |
| Windows and insulation | Aluminium without thermal break, single glazing, uninsulated shutter boxes, walls without a cavity | New PVC or thermally broken aluminium windows, insulated plasterboard linings |
| Floors and ceilings | Terrazzo, generous heights, plaster ceilings with mouldings, sometimes low suspended ceilings | Lay over or lift; suspended ceilings for services |
| Community and common areas | Rules on hours, small lift, facade due for rehabilitation | Rubble logistics, agreements for windows and stack |

At the technical visit we check these points and, if there are doubts, make exploratory openings in partitions and floors. It is the basis of the fixed itemised quote, and if you are buying, it can be done before you complete so you know what you are taking on.

## Services: electrics, lead and what lies behind the wall

**In a 1960s to 1980s flat the most important decision is to replace the electrical, water and waste services completely; it is the item that weighs most in the budget and the one that separates a renovation that lasts twenty years from a facelift.** Everything else (tiles, floors, kitchen) can be improved later; opening the walls twice cannot.

### Electrics: earth, circuits and aluminium

The installations of that era were designed for a home with few appliances. The norm is a fuse board or a single breaker, no RCD, no earth or a token one, two or three circuits for the whole flat and cable sizes too small for an oven, an induction hob, a water heater and several air conditioning units. In some 1970s buildings aluminium wiring was used, which degrades at the connections and is a fire risk. The solution is a new installation under the Spanish low-voltage regulations (REBT), with consumer unit, RCDs, separate circuits and earth, carried out by an authorised installer who issues the certificate (boletín). Without that certificate the electricity supplier will not increase your contracted power.

### Water and waste: lead, iron and asbestos cement

Lead pipes were used until the 1970s and galvanised iron until the 1980s. Lead contaminates drinking water; iron blocks with scale and rust and eventually bursts. The whole hot and cold network is replaced with modern pipe (cross-linked polyethylene or multilayer) and the wastes with PVC at the correct falls. The shared drainage stacks in asbestos cement or iron belong to the building: if the bathroom is opened up and the stack is in poor condition, its replacement has to be agreed with the community.

### Air conditioning

This is the moment to leave air conditioning pre-installation (pipes, condensate drain and electrical line) to every room, with the outdoor unit where the community allows, even if the units are bought later. Chasing walls after painting doubles the work.

## Damp, salt and walls: what decides the scope

**Damp and load-bearing walls are the two factors that most change the scope of an old flat renovation: damp means treating the substrate before finishing, and a load-bearing wall turns a layout change into major works with a project.** Both are detected at the technical visit, not in the second week of works.

### Damp

On ground floors in the Centro, Benalúa or Santa Cruz, rising damp appears: stains at the base of walls, blistering paint, salts. In north-facing or poorly ventilated bedrooms, condensation and mould. Near the sea, in Playa de San Juan or Albufereta, salt attacks render and ironwork. And in top-floor flats or those under a terrace, leaks. Each case has a different treatment and must be done before rendering and painting, because covered damp comes back within months. Our diagnosis is free and treatments range from €40/m² to €120/m², VAT not included, depending on the type. More on our [damp treatment in Alicante](/en/damp-treatment-alicante/) page.

### Load-bearing walls

1960s buildings often combine concrete columns with solid brick load-bearing walls, and in the 1970s and 1980s a column structure with hollow brick partitions predominates. But there is no safe rule: it has to be checked by thickness, position and, if necessary, an exploratory opening or a technician's inspection. Opening the kitchen to the living room or joining two bedrooms is feasible in both cases, but if the wall is load-bearing the works need a project with the reinforcement calculation, site supervision and a major works licence, which adds cost and weeks. We explain this in the guide on [when a major works licence is needed](/en/guides/major-works-licence-spain-when-needed/).

### Windows and insulation

The 1970s and 1980s aluminium windows without thermal break and with single glazing are the biggest loss of comfort in these flats: heat in summer, cold in winter, street noise. Replacing them with PVC or thermally broken aluminium with double glazing costs, indicatively, €350 to €900 per unit, VAT not included, respecting the community's criterion for the facade. An insulated plasterboard lining on the external walls completes the upgrade; see our [plasterboard in Alicante](/en/plasterboard-pladur-alicante/) page.

## The order of works in a full renovation

**The correct order for a full renovation is: demolition, services, masonry, finishes, suspended ceilings, joinery and kitchen, painting, sanitaryware and fittings, cleaning and handover. It exists so that each trade prepares the ground for the next and none damages the previous work.** Changing it is the cause of most snagging and cost overruns.

1. **Preliminary work and demolition.** Protection, stripping kitchen and bathrooms, lifting floors and tiles if they are being removed, taking down partitions (non-structural, or with propping and a project if they are), removing old joinery and services, rubble out.
2. **Services.** Chasing and running plumbing, drainage, complete electrics, air conditioning and telecoms pre-installation. Before closing, pressure tests and circuit checks.
3. **Masonry.** New partitions, closing chases, render, floor screeds with their drying times, door and window sub-frames, insulated linings.
4. **Windows.** Fitted after masonry and before finishes, so that the reveals are clean.
5. **Finishes.** Tiling bathrooms and kitchen, flooring throughout, plaster skim.
6. **Suspended ceilings.** Plasterboard or plaster where services need hiding, with the lighting cut-outs.
7. **Interior joinery and kitchen.** Doors, wardrobes, kitchen units, worktop.
8. **Painting.** Preparation, sanding, primer and finish. Always after joinery and before sanitaryware and switches, to protect what marks easily.
9. **Sanitaryware, taps, switches, light fittings, shower screens and air conditioning units.**
10. **Snagging, cleaning, testing, installer certificates and handover** with a written guarantee.

The schedule with durations per phase is in the guide on [how long a full renovation takes](/en/guides/how-long-does-a-full-renovation-take/).

## Renovating in phases if you live in the flat

**If you cannot move out during the works, renovate in phases but respect the order: first complete services and bathrooms, then kitchen, and finally floors, joinery and painting; never finishes before services.** It is slower and somewhat more expensive than doing it all at once, but it avoids opening the same thing twice.

A sensible sequence in a 90 m² flat with two bathrooms:

- **Phase 1: general services and main bathroom.** New consumer unit and circuits, new water network to every point, main bathroom complete. You live with the second bathroom and the old kitchen.
- **Phase 2: second bathroom and kitchen.** With the services already new, the kitchen is mainly masonry, finishes and units.
- **Phase 3: floors, joinery, windows and painting** by zones, moving furniture.

What should not be done in phases is the electrical installation (half a flat with a new installation and half with the old one is a safety and certification problem) or the water network, for the same reason.

For owners who are abroad most of the year, the opposite applies: an empty flat is the ideal condition for a single, continuous renovation, and we send photo and video updates at each phase so you do not need to be there.

## Common mistakes

- **Starting with the finishes.** Choosing tiles and kitchen before knowing which services need replacing is the way to run out of budget for what matters.
- **Changing "only what you can see".** New tiles over lead pipe and cable without earth is an incomplete renovation that will have to be redone.
- **Taking down a partition without checking if it is load-bearing.** In 1960s buildings it is a real risk; check it with an opening or a technician.
- **Covering damp with anti-damp paint.** It comes back within months. First diagnose and treat the source.
- **Leaving the windows for "later".** Fitting them after painting means redoing reveals and paint; and with the old ones, the renovated flat is still hot and noisy.
- **Not leaving air conditioning pre-installation.** Chasing a freshly painted flat is the classic example of poorly planned works in Alicante.
- **Forgetting the community.** Drainage stack, windows and the outdoor air conditioning unit affect common elements. We explain this in the guide on [community of owners permission for renovations](/en/guides/community-of-owners-permission-renovation-spain/).
- **Quoting without a visit or exploratory openings.** A quote for an old flat done from photos ends up full of extras.

## When to call a professional

**In an old flat, what you can do yourself is the groundwork: define what you want, read the community rules, gather any plans that exist and decide on quality levels. Everything involving services, structure and damp needs professionals, and in several cases qualified ones.** Painting and assembling furniture at the end is another matter.

The new electrical installation is carried out by an authorised installer who issues the certificate; without it there is no power upgrade or new supply contract. The water network, drainage and gas, if there is any, likewise. If a load-bearing wall has to be opened, the project and supervision are signed by a technician and the works need a major works licence. And diagnosing damp requires experience to tell rising damp, condensation and leaks apart, because each is treated differently.

At Costa Renova we do the technical visit within 48 to 72 hours in Alicante and the surrounding area, with exploratory openings if needed, and deliver a fixed itemised quote that includes handling the declaración responsable or licence with the town hall. You have a single project manager from start to finish and a written guarantee of the works. If you are thinking of renovating a 1960s to 1980s flat in the Centro, Carolinas, Benalúa, San Blas or on the coast, book the free visit from our [full home renovation in Alicante](/en/full-home-renovation-alicante/) page or from the [contact](/en/contact/) page.