# Pool maintenance after a renovation

After a renovation, a pool needs a careful start: continuous filling with no stops, starting the filtration with a clean filter, balancing the water (pH first, then sanitiser) before anyone swims, and a few weeks of watching the level, flanges and joints. After that, a simple weekly routine and proper overwintering from October to April protect the new reinforced liner or mosaic, which is where €4,000 to €15,000, VAT not included, has just been spent.


## Maintenance after the renovation: the short answer

**A freshly renovated pool is started up in this order: continuous filling to halfway up the skimmer, filtration started with a clean filter and a check for drips at flanges and in the plant room, water balanced (pH and alkalinity first, then sanitiser) without ever putting chlorine directly on the new finish, extended filtration for the first week, and a month of watching the level. After that, a ten-minute weekly routine and active overwintering from October to April protect an investment of €4,000 to €15,000, VAT not included.**

Those are the 2026 guide prices we work with in Alicante and within 45 km, the same ones on our [pool renovation in Alicante](/en/pool-renovation-alicante/) page. This guide is the one we hand to every client, in a short version, when a renovation is finished; here we expand it so it is useful even if someone else did the work. What we say about products and doses is general guidance: the exact dose is set by the manufacturer of each product and the volume of your pool.

If you own the pool from abroad, the first month is the part to plan around: either be in Spain for the start-up, or arrange for your key holder or pool maintenance person to follow the steps below and send you photos of the readings and the plant room.

## The first 72 hours: filling and start-up

**Filling and start-up are the moment when a well executed renovation can be spoilt; it is done slowly, with nobody swimming and with eyes on every fitting.**

### Filling

- **Continuous.** With a reinforced liner, filling without pauses tensions the liner evenly; stopping and restarting leaves creases that set. With mosaic, continuous filling avoids lime tide lines and marks on the new grout. If your supply flow is low, work out the time: an 8 x 4 m pool with an average depth of 1.5 m holds about 48 m³, and at a domestic flow rate that is many hours; sometimes it pays to order a water tanker.
- **Nobody in and no cleaner.** Until it is full and checked.
- **With a liner, smooth and retighten.** As the water rises, small creases are pushed towards the edges before the weight of the water fixes them, and as the water covers each fitting (main drain, inlets, lights, skimmer) its flange is retightened. The installer does this or leaves instructions.
- **To halfway up the skimmer.** No higher (the skimmer stops cleaning the surface) and no lower (the pump draws air).
- **With mosaic, only after curing.** The waterproof render, the adhesive and the grout need their curing times before taking water; filling early is the cause of tiles coming loose in the first month.

### Starting the filtration

1. Check the filter is clean (new sand or glass if it was changed; backwashed if not), the pump strainer basket empty and the valves set to filter.
2. Prime the pump: fill the strainer housing with water, close the lid with its O-ring seated properly and start. If the pump does not draw within a minute, stop and check lids and valves; a pump running dry burns out.
3. Bleed the air from the filter through its air release valve until water comes out.
4. Write down the pressure gauge reading with a clean filter: it is the reference for when to backwash.
5. Look for drips during the first 48 hours at: the strainer lid, pump to filter unions, the multiport valve, skimmer, inlet and light flanges, and the liner profile zone. A sheet of kitchen paper under each union shows up a single drop.
6. If the electrics were touched (board, RCD, lights, new pump), check that the RCD trips with its test button; anything abnormal is checked by an electrician, never bypassed.

## The water: balance before you sanitise

**The order is always the same: pH and alkalinity first, sanitiser second; a new finish suffers more from pH and chlorine extremes than from use.**

| Parameter | General reference | Why it matters after a renovation | How it is corrected |
|---|---|---|---|
| pH | Around 7.2 to 7.6 (usual reference) | High: scale on grout and liner, sanitiser works poorly. Low: aggressive water that attacks grout, metals and liner | pH reducer or increaser, in small doses, with the pump running, testing a few hours later |
| Alkalinity | Whatever keeps pH stable, per manufacturer | Without alkalinity the pH swings daily from one extreme to the other | Alkalinity increaser before touching the pH |
| Sanitiser (free chlorine or another system) | Within the manufacturer's range | Too much: liner bleaching, eroded grout, smell. Too little: algae in days | Dose through the skimmer, a dispenser or a chlorinator, never onto the finish |
| Hardness (calcium) | Moderate, per manufacturer | Very hard water leaves scale on mosaic and on the liner waterline; very soft attacks renders and grout | Per test; mains water in Alicante is usually hard |
| Stabiliser (cyanuric acid), if chlorine is used | Within the manufacturer's range | In excess, chlorine stops sanitising even though it tests fine | Replace part of the water if it builds up |

Practical rules for the first days:

- Test every day in the first week (strips or a drop kit; a photometer if you want precision) and then twice a week in summer.
- Correct gradually: half a dose, wait a few hours with the pump running, test again. Sudden changes are worse than a reading slightly off.
- Add products dissolved or through the skimmer with the pump running. Never tablets or granules on the floor: on a reinforced liner they leave a permanent bleached patch; on mosaic they attack the grout.
- Salt chlorination: if the renovation included a salt chlorinator, the salt is added to the water according to the volume and left to dissolve before switching the cell on; pH tends to rise and needs closer watching.
- Filter for long hours in the first week (more than usual, even continuously for the first two or three days) to clear the water and settle everything; after that, in summer, as many hours as it takes to turn the volume over at least once or twice a day, depending on your pump's flow.

## The first month: watch the level, flanges and finish

**During the first month after the renovation there are three things to watch: that the level does not drop more than evaporation, that no flange or union drips, and that the finish settles without creases, loose tiles or stains.**

- **Level.** Mark the level on the skimmer and compare it every few days. In summer in Alicante evaporation is noticeable; if in doubt, do the bucket test: a bucket of pool water on the step, marked at the same level as the pool, and compared after a day or two. If the pool loses more than the bucket, tell the company without waiting: flanges, welds, finishing details and fittings are covered by the written guarantee, and a leak behind the liner creates bubbles that cost more the longer they are left.
- **Flanges and unions.** With the water at its level and the pump running, check the skimmer, inlet, main drain and light flanges again; sometimes they need retightening after a few days of water pressure. In the plant room, look every week.
- **Reinforced liner.** Small ripples in the first weeks can be normal with temperature changes; bubbles that grow are not. Clean the waterline with a soft sponge and a specific product; no stiff brushes or abrasive products. The cleaner must be suitable for liners.
- **New mosaic.** The odd loose tile in the first weeks is refixed with a specific adhesive; several, tell the company. New grout is protected by avoiding acidic water and brushing with a bristle brush, never metal.
- **New equipment.** Pump, filter, chlorinator or LED lights: keep the manufacturers' manuals and guarantees separately from the guarantee on the work. The two cover different things and it helps to have both to hand if you ever need to claim.

## The weekly routine in season

**Ten minutes a week keeps a renovated pool in good condition; what gets neglected is the grout, the waterline and the filter.**

1. **Test and adjust** pH and sanitiser. In heatwaves, with heavy use or after a storm, test more often.
2. **Empty the baskets** in the skimmer and the pump strainer. On estates with pine trees (Mutxamel, Busot, Sant Joan, La Vallonga), every two or three days in spring.
3. **Brush walls and waterline** with the brush suited to the finish. The waterline collects body oils, sun cream and scale; a specific product each week stops the permanent tide mark.
4. **Run the cleaner**, manual or automatic, suited to your finish.
5. **Check the filter pressure** and backwash (backwash and rinse) when it rises clearly above the start-up pressure. After backwashing the level drops: top up.
6. **Look in the plant room**: drips, pump noise, timer. And check the water is still halfway up the skimmer.
7. **After storms and the autumn downpours** (the DANA events that hit the Valencian coast): rainwater, dust and leaves throw pH and chlorine out within hours; test, empty baskets and filter longer.

A note on running costs: a variable-speed pump, if the renovation included one, is programmed at low speed for many hours rather than full power for a few; it filters better and costs less to run.

## Overwintering in Alicante: do not drain, do look after it

**In Alicante the pool is not drained in winter: you do active overwintering with reduced filtration, balanced water, a winterising product and, if possible, a cover, and check it every two or three weeks.**

Why not drain: an empty shell in areas with a high water table (the front line in San Juan, Albufereta, Santa Pola, Guardamar, Torrevieja, or any plot after heavy rain) can float or crack; a reinforced liner with no water over it shrinks and fades in the sun; mosaic and grout dry out and craze. Our renovations are scheduled from October to April precisely because the pool is out of use then, not because it is empty. If you spent your working life in the UK thinking of winter as the time to drain and cover, this is the one habit to unlearn.

Active overwintering, step by step, at the end of the season (in Alicante, when the water temperature drops steadily, usually between October and November):

1. Thorough clean: baskets, floor, walls, waterline; backwash the filter.
2. Balance the water: pH and alkalinity in range, sanitiser in range.
3. Add a winterising product as the manufacturer directs, which holds back algae and scale during months of little filtration.
4. Reduce filtration to a few hours a day, preferably the coldest hours to discourage algae, and keep the water halfway up the skimmer.
5. Fit a winter cover if the pool allows it: less dirt, less evaporation, fewer algae and more safety.
6. Check every two or three weeks: level, baskets, pH, look of the water; after easterly gales or a DANA, sooner.
7. On the few frosty nights inland (Elda, Petrer, Novelda), protect the pump and exposed pipework in the plant room; on the coast it is rarely needed.

In spring, the start of the season is far easier if overwintering was done properly: clean, backwash, balance, go back to summer filtration and, if needed, a shock treatment before the first swim. For a holiday home or rental, this fits the between-seasons checklist in our guide on [renovating a holiday rental between seasons](/en/guides/renovating-a-holiday-rental-between-seasons/).

## Typical problems after a renovation and what they mean

**Almost every first-year problem comes from unbalanced water or a rushed fill and start-up, and most have a simple fix if you act early.**

| Symptom | Likely cause | What to do |
|---|---|---|
| Cloudy water in the first days | New filter shedding fines, mains water with particles, chemistry not settled | Filter longer, backwash, balance; if it persists, flocculant per manufacturer |
| Dark or scaly waterline | Oils and sun cream; high pH and hardness | Clean with a specific product, lower pH, test hardness |
| Pale patches on the liner | Granular chlorine or a tablet in direct contact | No way back; avoid it from now on |
| Creases or a growing bubble in the liner | Water behind the liner: leak at a flange or water table; poor tensioning | Tell the company under the guarantee |
| Tiles coming off | Filled before curing, wrong adhesive | A few: refix; several: tell the company |
| Green algae within days | Low sanitiser, little filtration, heat | Brush, shock treatment, continuous filtration, check the filter |
| Noisy pump or drawing air | Low level, strainer lid not sealed, suction leak | Top up, check the O-ring; if it continues, a pool plumber |
| Level dropping more than the bucket | Leak at a flange, weld, fitting or pipe | Tell the company; do not add sealants |
| Lights not working or RCD tripping | Damp in the niche, cable gland | Electrician; do not touch with the pool full and power on |

Plant room plumbing is handled by our own team, and the small maintenance tasks you would rather not do yourself (start-up cleans, filter media changes, winter checks) can be done by our partner [Manitas Costa](https://manitascosta.es/en/), who is also the company owners abroad use for the monthly look at a closed house.

## Common mistakes

- **Stopping the fill halfway.** Creases set in the liner and tide lines on the mosaic.
- **Swimming before the water is balanced and sanitised.** Uncontrolled water and a finish that suffers from day one.
- **Putting chlorine straight onto the liner or mosaic.** Stains and attacked grout with no remedy.
- **Correcting the pH in one go.** Swings that attack grout and metals; half a dose and test.
- **Forgetting the filter.** Without backwashing, the water clouds however much chemistry you add.
- **Using a cleaner or brushes unsuited to the liner.** Marks and punctures.
- **Letting the level drop below the skimmer.** A pump that draws air and burns out; a liner exposed to the sun.
- **Draining in winter.** Risk of the shell floating and damage to the finish; active overwintering instead.
- **Waiting months to report a loss.** The guarantee covers it, but a leak behind the liner costs more the later it is found.

## When to call a professional

**The weekly routine, testing and correcting the water, cleaning and basic overwintering are yours; leaks, equipment, electrics and any crease, bubble or loose tile in the first year belong to the company that did the work.**

You can do yourself: everything in the weekly routine, balancing the water with a test kit, backwashing the filter, cleaning baskets and the waterline, active overwintering and the spring start-up, and the bucket test if you suspect a loss.

You need a professional for any confirmed leak (flanges, welds, fittings, pipes), to retighten or replace light and skimmer flanges, to repair a liner (welded patches) or refix mosaic beyond a few tiles, to change the filter sand or glass if you would rather not, for any electrical work (lights, board, pump, chlorinator), which must comply with the Spanish low-voltage regulations, and for community pools, which have their own health and registration requirements and usually have a contracted maintenance firm.

If we did the renovation, we do the start-up with you and the written guarantee on the work covers anything that fails in finishing details, welds and fitted parts. If you are thinking about renovating and want to know what is included and what it costs, we explain it in [pool renovation cost in Spain](/en/guides/pool-renovation-cost-spain/). We visit within 48 to 72 hours in Alicante and the surrounding area and give you a fixed itemised quote, free and without obligation, with the work scheduled from October to April and photo updates if you are not in Spain. See our [pool renovation in Alicante](/en/pool-renovation-alicante/) service or book your visit through [contact](/en/contact/).