# Major works licence (licencia de obra mayor): when you need one and what it involves in Alicante

You need a major works licence when the works affect the structure (load-bearing walls, columns, floor slabs), the facade or the roof, change the use of the property or increase its volume. It requires a technical project signed by an architect or technical architect, site supervision by that technician and a formal decision from the town hall before you start. This guide explains how to tell whether your renovation counts as major works and what that means in time, money and paperwork.


## What a major works licence is and when you need one

**A major works licence (licencia de obra mayor) is the municipal authorisation you need when your works affect the structure, the facade, the roof, the volume or the use of a building, and its defining feature is that it requires a technical project signed by an architect or technical architect and a formal decision from the town hall before you start.** It is the procedure with the most control because these are works that can affect the safety of the building, the neighbours or the urban environment.

For most home renovations it is not needed: a bathroom, a kitchen, floors or partitions go through a declaración responsable or a minor works licence. But there is a group of jobs that many owners, especially those used to UK permitted development rules, think of as "just another renovation" and that are in fact major works: opening the kitchen to the living room by removing a load-bearing wall, glazing in a terrace, converting a commercial unit into a flat, extending a villa, replacing the roof of a chalet, joining two flats. In those cases, trying to pass it off as minor works ends in a stop order.

This guide helps you recognise whether your works are major, what documents and which technician you need, how the process works at the Ayuntamiento de Alicante and in the surrounding municipalities, and what mistakes to avoid. If your works are clearly interior with no structural impact, the guide on the [minor works licence in Alicante](/en/guides/minor-works-licence-alicante/) is the one to read.

## Major or minor works: a table of frequent cases

**Works are major if they touch structure, facade, roof, volume or use; they are minor if they stay inside without affecting any of those.** This table covers the cases that raise most questions in flat and villa renovations in Alicante. It is a guide: the final classification is made by the town hall under its rules.

| Job | Major or minor | Why |
|---|---|---|
| Renovating bathroom, kitchen, floors, painting | Minor (declaración responsable) | Does not affect structure or facade |
| Moving hollow brick or plasterboard partitions | Minor | Non-structural elements |
| Opening a load-bearing wall | Major | Affects the structure; needs calculation and reinforcement |
| Removing a column or touching a floor slab | Major | Affects the structure |
| Replacing windows in the same opening | Minor (with community agreement) | Does not alter the facade composition |
| Glazing in a terrace or balcony | Major in most cases | Modifies facade and volume |
| Extending a villa or adding a floor | Major | Increases built volume |
| Replacing the roof of a chalet | Major depending on scope | Affects a structural element and the envelope |
| Change of use from commercial premises to home | Major | Changes the use; must meet habitability rules |
| Joining or splitting flats | Usually major | Usually affects structure and the number of dwellings |
| Facade rehabilitation with scaffolding | Depends on scope; separate scaffolding permit | Affects a common element and the public road |
| Building a new swimming pool | Major | New construction with structure |
| Rehabilitating an existing pool (shell, lining) | Usually minor | Creates no new volume |

## What a major works licence requires: project, technician and site supervision

**A major works licence requires a technical project signed by an architect or technical architect, the appointment of site supervision (dirección facultativa), in many cases a health and safety study, payment of fees and ICIO per ordinance and, at the end, the final works certificate.** It is more paperwork than minor works, but each piece has a purpose.

### The technical project

This is the central document. It describes the works with a report, drawings, calculations (for example, of the reinforcement for a load-bearing wall), measurements and a cost estimate, and justifies compliance with the Spanish Building Code (CTE) and planning rules. Depending on the job, it can be split into a basic project (for the licence) and an execution project (for building). It is drafted by an architect or, for works within their remit, a technical architect.

### Site supervision (dirección facultativa)

The technician who signs the project, or another one appointed, supervises the works: checks that what is built matches the project, resolves surprises (very common in older buildings), signs the site order book and issues the final works certificate. In works involving structure there is also an execution supervisor, normally a technical architect. For an owner managing from abroad, this is the independent professional who confirms the works were done as designed.

### Health and safety, waste and other documents

Depending on the scope, the town hall will ask for a health and safety study or basic study, a construction and demolition waste management plan and, if there is scaffolding or a skip on the street, a public road occupation permit. For works on common elements, the community of owners' agreement. And for changes of use, proof of habitability conditions, followed by the first or second occupation licence.

### Fees, tax and professional fees

The licence attracts municipal fees per ordinance and the tax on constructions, installations and works (ICIO), on the cost of the works. Separately there are the technician's fees for the project and supervision, which depend on the size and complexity of the job. We do not quote fee figures; the partner technician's fees appear as a separate line in our quote, apart from the building works.

## Typical major works cases in Alicante renovations

**In Alicante, the most frequent major works in renovations are opening load-bearing walls in older flats, terrace enclosures in coastal apartments, extensions and roofs on villas, and changes of use from commercial premises to homes.** Each has its own particularities.

### Opening a load-bearing wall in a 1960s to 1980s flat

In many flats in the Centro, Carolinas, Benalúa, San Blas or the Ensanche, the structure combines columns with solid brick load-bearing walls, especially in 1960s buildings. Opening the kitchen to the living room usually involves a load-bearing wall. The project calculates the reinforcement (normally a steel frame or a lintel), defines the temporary propping during the works and the site supervisor controls execution. It is a common and safe job if done with a project; without one, it is a real risk to the building. Our guide on [renovating an old flat in Spain](/en/guides/renovating-an-old-flat-in-spain-where-to-start/) explains how to identify these walls before planning.

### Glazing in a terrace in a coastal apartment

In Playa de San Juan, Albufereta, Cabo de las Huertas, El Campello or Gran Alacant this is one of the most frequent enquiries from British and Irish owners. The enclosure modifies the facade and, in most cases, the buildable volume, so it requires a licence (often major works) and an agreement of the community of owners. Many communities have a prior agreement with an approved enclosure design to keep the facade uniform; even so, the municipal procedure is still necessary. Check this before counting those square metres as part of the home, and certainly before buying on that assumption.

### Extending or replacing the roof of a villa

In the urbanisations of Vistahermosa, Cabo de las Huertas, Mutxamel, Busot or San Vicente, adding a floor, covering a porch or replacing a roof is usually major works. The project must check the buildable area remaining on the plot, the setbacks and, where a roof is involved, the structure. You can see how we approach this kind of job on our [villa renovation in Alicante](/en/villa-renovation-alicante/) page.

### Change of use from commercial premises to home

Converting a ground-floor commercial unit into a flat requires checking that planning rules allow it in that building and that street, meeting habitability conditions (floor areas, ventilation, light, ceiling height), drafting a project, obtaining a major works licence and a change of use licence, and finally the occupation licence. Not every unit qualifies, so this is something to check before signing a purchase.

### Facade and roof rehabilitation in communities

Facade rehabilitation with scaffolding on 1960s to 1980s buildings, very common because of spalling and salt damage near the sea, can be major or minor works depending on scope (surface repair versus replacing elements). It always requires a community agreement and a public road occupation permit for the scaffolding. More detail on our [facade renovation in Alicante](/en/facade-renovation-alicante/) page.

## How the major works licence process works

**The process has five phases: preliminary study and feasibility, drafting the project, filing and processing at the town hall, execution with site supervision, and closure with the final works certificate.** Understanding the order avoids hiring people at the wrong moment.

1. **Preliminary study.** Before commissioning a project, a technical visit is advisable to check the structure, the planning constraints and the community's conditions. This is the moment to find out whether the works are feasible and which procedure they need.
2. **Technical project.** The partner architect or technical architect drafts the project. In parallel, the community agreements are prepared if common elements are affected.
3. **Filing and processing.** The project is filed with the application, the self-assessed fees and ICIO and the supporting documents. The town hall issues technical and legal reports and, if needed, requests. You cannot start until the decision.
4. **Execution.** The works are carried out according to the project, with site supervision, an order book and, where applicable, health and safety coordination. Significant changes are documented as project modifications.
5. **Closure.** The technician issues the final works certificate; for changes of use or new dwellings, the occupation licence is also processed. Keep all the documents: you will need them to sell, let or insure the property.

At Costa Renova we coordinate all phases with partner technicians and carry out the works, so you have a single project manager from start to finish. If you already have your own architect, we work with them.

## Common mistakes

- **Processing as minor works something that is major.** This is the most expensive mistake: stop order, new procedure with a project, and sometimes a penalty. If there is any doubt about a wall, it is checked first.
- **Commissioning the project without checking feasibility.** An enclosure the community will not approve or an extension that exhausts the buildable area is money lost in fees.
- **Starting the works before the decision.** With a major works licence there is no exception: until it is decided, you cannot start.
- **Forgetting the community of owners.** Facade, roof, terraces and structure are common elements. Without an owners' meeting agreement, the town hall can refuse and the neighbours can demand reinstatement. We explain this in the guide on [community of owners permission for renovations](/en/guides/community-of-owners-permission-renovation-spain/).
- **Dropping site supervision "to save money".** In works involving structure, the technician is the one who decides how to prop and when to remove the props. It is not an optional cost.
- **Not allowing for surprises in older buildings.** Opening a 1960s wall can reveal beams in poor condition, ducts or unexpected services. A margin of time and budget avoids shocks.
- **Buying a commercial unit intending to convert it without checking the rules.** Not every unit can change use. Ask before you sign.

## When to call a professional

**If your works touch structure, facade, roof, volume or use, there is no do-it-yourself version: you need a technician to sign the project and a company to build under supervision.** What you can do yourself is the analysis phase: decide what you want, read the community statutes and ask for a technical visit before committing money.

There are also safety and liability reasons. A badly propped load-bearing wall can cause cracks on several floors; an enclosure without a licence may have to be demolished; a change of use without the procedure prevents you from registering utilities or selling the property normally. And new services (electrics, gas, water) require authorised installers and their certificates in any case.

We do not employ architects in-house: we work with partner architects, technical architects and engineers who draft the project and take on site supervision, while we build and coordinate. If you are thinking of opening a wall, glazing in a terrace, extending your villa or converting a commercial unit, book the free technical visit: we tell you whether the works are feasible, which procedure they need and give you a fixed itemised quote, with the building works, the paperwork and the technician's fees shown separately. You can request it from the [contact](/en/contact/) page, and read more about how we handle larger projects on our [full home renovation](/en/full-home-renovation-alicante/) page.