# Living in your home during a renovation: how phased works are organised

You can live in your home during a renovation if the job is split into phases, one bathroom is always working, a sealed clean zone is set up and the order of works is respected: strip-out and services across the whole property first, then finishes room by room. A full renovation of a 70 to 100 m² flat takes 8 to 14 weeks with the property empty; done in phases it takes somewhat longer, but you avoid paying for temporary accommodation. This guide explains how it works and when it is not worth it.


## It can be done, but it is not always worth it

**Living in your home during a renovation is possible if the job is split into phases, one bathroom and a sealed clean zone are always kept, and the order of works is respected: services across the whole property first, finishes room by room afterwards.** It is worth it when the alternative is weeks of expensive temporary rent and the property has enough space to separate living from building. It is not worth it when the only bathroom is being renovated, when floors and services are being replaced throughout, when there are small children, or when you work from home with nowhere else to go.

We see it often in Alicante: a couple who have bought a 1970s flat in Carolinas or Benalúa, want it fully renovated and do not want to pay rent while it happens; owners of apartments in Playa de San Juan renovating in winter while living in one bedroom; villas in San Vicente or Mutxamel where the ground floor is renovated while the family lives upstairs. It works if it is planned. This guide explains how, in the same terms a Spanish builder will use with you.

Here we assume you already have a fixed, itemised quote and a company willing to work in phases. If you are still deciding where to start with an older property, read [renovating an old flat in Spain: where to start](/en/guides/renovating-an-old-flat-in-spain-where-to-start/) first.

## Table: the order of phases and what you need in each one

**A phased renovation always follows the same pattern: one general phase of strip-out and services, then finishes by zone, leaving the living room, hallway and painting for last.** This table shows a typical schedule for a 70 to 100 m² flat with two bathrooms.

| Phase | What is done | Where you live | What must be working |
|---|---|---|---|
| 0. Preparation | Partial clearing, protection, sealing the clean zone | Living bedroom + bathroom 2 | Bathroom 2, temporary or existing kitchen |
| 1. Strip-out and general services | Tile removal, chasing, new plumbing and electrics, air conditioning pipework | Living bedroom (better away on strip-out days) | Bathroom 2, a water point, temporary lighting |
| 2. Main bathroom | Tiling, shower tray, sanitaryware, taps | Living bedroom | Bathroom 2 |
| 3. Kitchen | Building work, tiling, units, appliances | Living bedroom | Bathroom 2 + temporary kitchen |
| 4. Bedrooms | Plasterboard, floors, internal doors | Move into a finished bedroom | New main bathroom |
| 5. Bathroom 2 | Renovation of the second bathroom | Finished bedroom | New main bathroom |
| 6. Living room, hallway and painting | Continuous floors, doors, painting throughout, snagging | Finished bedroom | Everything above |
| 7. Handover | End-of-works clean, inspection, written guarantee | The whole home | - |

The reference timelines are the ones on our prices page: a bathroom renovation takes 2 to 3 weeks, a kitchen renovation 3 to 5 weeks, a full flat renovation 8 to 14 weeks (70 to 100 m²). In phases some trades cannot overlap and there are days of moving, protecting and cleaning between phases, so the total is longer. The guide on [how long a full renovation takes](/en/guides/how-long-does-a-full-renovation-take/) explains what drives it.

## The order of works: why services go first

**Services (water, electricity, air conditioning) cross every room through ceilings, floors and walls, so they are done once across the whole property before anything is closed up; after that, finishes can be done zone by zone.** This is the rule that separates a well-planned phased renovation from one that forces you to reopen finished rooms.

It has a practical consequence: phase 1 is the worst one to live through. Removing tiles, chasing walls and running pipes generates noise and dust in every room for one or two weeks. If you can be away for those days (family, a holiday, an off-season apartment), do it; it is the single decision that most improves the experience. From then on the phases are localised and living next to them is manageable.

Other points about the order worth knowing:

- **The consumer unit is replaced at a specific moment** and the home is without power for a few hours. The company warns you the day before.
- **Water cuts** are brief (connecting new feeds, changing stopcocks), but the water in a room under renovation may be off for weeks.
- **Continuous flooring** (the same floor throughout the home) is the main obstacle to living in. The whole property has to be empty. If you are staying, consider floors by room with thresholds, or lay the living room and hallway floor in the last phase, when you are already sleeping in a finished bedroom.
- **Painting goes at the very end**, when no trade is left that makes a mess. Painting a finished room and carrying on with works next door guarantees touch-ups.
- **Air conditioning and aerotermia (air-source heat pump) equipment** go in during phase 1 (pipework) and the last phase (units and commissioning), so new machines do not fill with dust.

If the flat is old there is an added risk: once walls are opened, surprises appear (a load-bearing wall where a partition was expected, asbestos-cement soil stacks, wiring with no earth) and change the plan. The guide on [renovating an old flat in Spain](/en/guides/renovating-an-old-flat-in-spain-where-to-start/) covers the usual ones.

## A temporary bathroom and kitchen

**The critical point of living in during the works is always having a toilet, a shower and a water point for cooking; if the property has two bathrooms they are renovated one after the other, and if it has only one you need a real alternative for the 2 to 3 weeks of bathroom works.** This is the first thing to settle before deciding to stay.

### With two bathrooms

The usual arrangement: the main bathroom is renovated while the second is used, then the order is reversed. Ask for the bathroom in use to be kept outside the works zone, with its door sealed on the works side, and for the hot water not to be cut without warning.

### With one bathroom

The realistic options:

- **Showering elsewhere**: gym, family, a trusted neighbour. For 2 to 3 weeks many households can manage; with small children, less so.
- **A temporary toilet**: some jobs allow the toilet to stay connected until the last moment and be refitted quickly; it depends on whether the drain is moving. Ask explicitly.
- **A temporary shower tray** in the utility room or kitchen, where there is a drain and a water feed. Not always possible and it has a cost; it is one more line in the quote.
- **Replacing only the bath with a shower tray** instead of a full renovation: it takes 1 to 2 days, costs €950 to €2,200, VAT not included, and the toilet and basin usually stay in use. If your priority is not leaving home, this is the most comfortable solution. Details on the [bath to shower conversion in Alicante](/en/bath-to-shower-conversion-alicante/) page.

To know exactly which days of the bathroom schedule there will be no shower, the guide on [how long a bathroom renovation takes](/en/guides/how-long-does-a-bathroom-renovation-take/) breaks down the stages.

### A temporary kitchen

A kitchen renovation takes 3 to 5 weeks. Set up a temporary kitchen beforehand: a table in the living room or a bedroom with a portable induction hob, microwave, kettle and the fridge (if it fits through the door and there is a socket). The water point will be the bathroom or the utility room; if the utility room has a washing machine tap, even better. Agree with the company when the kitchen water and gas are cut off and where the crockery you need is kept.

## Dust, noise and sharing the home with a building site

**Dust is controlled by sealing the clean zone, protecting the access corridor and cleaning daily; noise is managed by agreeing working hours; coexistence works with a single project manager on site and clear rules from day one.** Three separate fronts.

### Dust

- A clean zone sealed with plastic sheeting and tape, or with a zipped site door that lets you in and out without leaving a gap.
- Ventilation grilles and air conditioning units covered for the whole job.
- Access corridor with floor protection and, if possible, a damp mat at the entrance to the clean zone.
- Daily cleaning of the living zone: fine building dust settles again every night.
- The workers must clean the access route at the end of each day. It is a reasonable requirement; ask for it.

In coastal homes, with windows open because of the heat, dust travels further. And in city-centre flats with an internal light well (patio de luces), that well is how dust reaches the neighbours: closing the windows onto it during strip-out avoids complaints.

### Noise

Communities of owners (comunidades de propietarios) usually set working hours; in coastal blocks it is common for works to be banned in high season (July and August). Within that framework, agree the strip-out and demolition days with the company so you know when to leave if you can. Tell the neighbours those specific days: a note in the lift saying "Tuesday and Wednesday there will be demolition noise" reduces tension a great deal. If your block has rules on works, our guide on [community of owners permission for renovations](/en/guides/community-of-owners-permission-renovation-spain/) explains what to check.

### Coexistence

Having a single project manager from start to finish is what makes living in bearable: one person to ask, to agree hours with, who knows which door is sealed and why. Set simple rules from day one: which areas belong to the works and which do not, where tools are stored, where people eat, where they smoke (outside), who locks up when leaving. And accept that for a few weeks your home is a building site: the sooner you take that on board, the less friction.

## When living in is not worth it

**It is not worth staying when the works affect the whole property at once (continuous floors and full services), when the only bathroom is being renovated, when babies, elderly people or anyone with respiratory problems live there, or when you work from home with no alternative.** In those cases, leaving for a few weeks, even just for phase 1, is a decision about health and timeline, not comfort.

To decide, compare real numbers: the cost of a temporary rental or staying with family during the weeks of works, against the extra cost of doing the renovation in phases (more site days, protection, temporary bathroom or kitchen) and the discomfort. In Alicante, out of season, a short-let apartment in Playa de San Juan, El Campello or Santa Pola can be a temporary solution that is easier to find than in summer, and it is one reason many flat renovations are done from October to May. For owners who split the year between Spain and the UK or Ireland, the easiest version is to schedule phase 1 for a period you are abroad anyway.

A middle way that works very well: leave the property only during phase 1 (strip-out and services, the hardest part) and come back for the finishing phases, which are localised and far easier to live with.

## Common mistakes

- **Starting the finishes in one room before the general services are done.** It forces you to reopen finished work to run a pipe or a cable. It is the most common technical error in a badly planned phased renovation.
- **Not having a guaranteed working bathroom.** Discovering on strip-out day that the toilet is going and there is no alternative.
- **Choosing continuous flooring throughout and wanting to live in.** The two do not go together; either thresholds by room, or leave for a few weeks.
- **Sealing the clean zone badly.** A sheet of plastic with a two-centimetre gap lets dust through as if it were not there.
- **Not agreeing the noisy days in advance.** Neighbours tolerate the works they know about and complain about the ones that surprise them.
- **Painting in phases.** Every room painted while there are works next door needs touching up at the end; paint everything together in the last phase.
- **Leaving the air conditioning uncovered.** Dust in the evaporator is a breakdown in the medium term that nobody covers.
- **Assuming the timeline will be the same as with the property empty.** It is not. Accept the phased schedule from the quote stage, in writing.

## When to call a professional

**You can organise the clean zone, the temporary kitchen, the protection and the relationship with the neighbours yourself; what requires a company is planning the technical order of phases, keeping the temporary services safe and coordinating the trades so each phase is closed before the next opens.** A badly coordinated phased renovation is the one that overruns most and generates the most snagging.

Before signing, ask the company for three specific things:

- **A written phase-by-phase schedule**, showing which room is touched each week and what stays working. It should be in the quote or attached to it.
- **A plan for the temporary services**: which bathroom is used, where the temporary kitchen goes, how the living zone gets light and water during phase 1.
- **A single project manager** to call. If you are passed from one trade to another, living in becomes a daily exercise in conflict management.

For owners who are not in Spain full time, add a fourth: photo and video updates at the end of each phase, so you can check the sealed-off work (new pipework, wiring) before it is covered. We plan phased renovations during the free technical visit, with a fixed itemised quote and a realistic schedule, and one English-speaking project manager from start to finish. If you are planning a [full renovation of your flat in Alicante](/en/full-home-renovation-alicante/) while living in it, or want to start with a [bathroom renovation](/en/bathroom-renovation-alicante/) without leaving home, tell us through the [contact](/en/contact/) page and we will tell you honestly whether it makes sense to stay or to move out.