# Business licence and opening a shop or bar in Alicante

Opening a business in a commercial unit needs two different permissions: one for the works and one for the activity. Depending on the activity and the town hall, opening goes through a declaración responsable or a licence, always with a technician, and the fit-out itself (€300 to €800 per m², IVA not included, 4 to 10 weeks) sits between the two procedures.


## What permission do you need to open a unit? The short answer

**To open a business in a commercial unit you generally need two separate authorisations: one for the fit-out works and one for the activity.** The first is processed through a declaración responsable, a licencia de obra menor or a licencia de obra mayor, depending on scope. The second is processed through a declaración responsable of activity or a licence, depending on the type of business and your town hall's ordinance.

This guide speaks in general terms. Thresholds, forms, fees and timescales vary between the Ayuntamiento de Alicante, Elche, Benidorm and any other municipality in the province. Use it to understand the route and the questions to ask, and confirm the detail with the technician who signs your file or with the town hall itself.

## Declaración responsable or licence: the practical difference

**With a declaración responsable you start under your own responsibility once the paperwork is filed; with a licence you wait for the town hall to grant it.** In both cases you must comply with the rules, and the town hall can check afterwards. The difference lies in who gives the first approval.

| Route | How it works | Usually applied to | What to bear in mind |
|---|---|---|---|
| Declaración responsable or notification | You file the documents and the technician declares compliance; you can start as far as the town hall allows | Low-risk activities and interior works not affecting structure | The town hall checks afterwards; if something fails it can order corrections or closure |
| Minor works licence | The town hall authorises simple works | Interior refurbishments of limited scope | Usually asks for a description and a budget for the works |
| Major works licence with project | Project signed by a technician, and a municipal resolution | Works touching structure, facade or changing the use | Longer timescales and a full project |
| Activity licence | Prior authorisation to carry on higher-impact activities | Hospitality, units with music, clinics, activities with smoke or high capacity | Needs installation reports and sometimes reports from other authorities |

To see when each works title applies, read our guides on [declaración responsable for building works](/en/guides/declaracion-responsable-building-works-spain/) and [when you need a major works licence](/en/guides/major-works-licence-spain-when-needed/).

## The right order: from viable unit to opening day

**The order that wastes the least money is: viable unit, technical project, works, then opening.** Skipping a step is usually expensive, because the works are built to what the project says and opening depends on the works being properly documented.

### 1. A viable unit

Before you sign anything, check that the unit allows your activity. Three things decide almost everything: the use permitted by the planning rules where the unit is, the statutes of the community of owners if there are homes above, and the physical conditions of the unit (clear height, a possible smoke outlet, toilets, accessibility, electrical power). A cheap unit that does not allow your activity is the most expensive mistake on the list.

If you are about to rent, try to get a condition precedent in the lease: that the signing depends on being able to obtain opening for your activity. That is a conversation with the landlord and your lawyer, not the builder, but it changes the risk a great deal.

### 2. Technical project

The competent technician (architect, technical architect or engineer, depending on the works and the activity) prepares the documents the town hall asks for: a descriptive report, drawings, a justification of regulations, installations and, where appropriate, a full project. Our guide on [what a commercial unit renovation project includes](/en/guides/commercial-unit-renovation-project-what-it-includes/) gives the detail.

This is the moment to decide the layout, capacity, toilets, ventilation and air conditioning, because the project sets what will later be required on site.

### 3. Fit-out works

The builder carries out the project. In a commercial unit, the fit-out costs €300 to €800 per m², IVA not included, and hospitality with installations €600 to €1,200 per m², over 4 to 10 weeks. The installations (electrics, air conditioning, plumbing, extraction where relevant) are done at this stage with their certificates and reports, because without them the file cannot be closed.

What you are entitled to ask of whoever builds: that the quote items match the project, that nothing changes without telling the technician, and that at the end they hand over the documents for each installation.

### 4. Completion and opening

When the works finish, the technician issues the completion certificate or certificate of compliance. With that and the installation certificates, the opening notification is filed or the activity licence requested. In some cases the town hall inspects before giving the go-ahead. Until that procedure is resolved, do not open to the public.

## Who does what

**The owner files and answers for it; the technician signs and processes; the builder builds and documents.** Mixing these roles is the most common cause of delays.

| Who | What they do |
|---|---|
| Business owner | Applies or declares; decides the activity; pays fees and taxes |
| Competent technician | Checks viability, prepares the report or project, signs, files and issues the completion certificate |
| Builder | Carries out the works to the project, hands over certificates and guarantees |
| Town hall | Checks, grants or inspects; may require corrections |
| Other authorities | Involved depending on the sector (health, industry, consumer affairs); not always the same ones |

At Costa Renova we carry out the works and handle the works declaración responsable, and we coordinate timings with your technician so the works do not wait for the paper and the paper does not wait for the works. The activity licence is filed by the owner with their technician.

## What changes with the type of business

**The greater the impact of the activity on neighbours and safety, the more paperwork and inspection there is.** Without quoting figures or thresholds, which depend on each municipality, the pattern is this:

- **Office, studio, shop without food handling:** usually the lightest route, with interior works and a low-risk activity.
- **Clinics, beauty, academies, gyms:** add requirements on capacity, ventilation, accessibility and sometimes the rules of their own sector.
- **Food and hospitality:** add food hygiene, extraction, noise and capacity. See the page on [restaurant and bar renovation cost](/en/prices/restaurant-and-bar-renovation-cost-alicante/), and in Spanish the page on [bares, restaurantes y hoteles](/reformas-bares-restaurantes-hoteles-alicante/) and the guide on [restaurant kitchens and extraction](/guias/reforma-de-cocina-de-restaurante-extraccion-de-humos-y-requisitos/).
- **Units with music or live shows:** usually need an acoustic study and extra soundproofing conditions.

## Particulars of Alicante and the province

**Alicante mixes ensanche units, ground floors of older blocks and tourist areas, and each situation brings its own obstacles.** Some real examples of what a technician finds:

- In the centre and in blocks of flats from the 1960s to the 1980s, ground-floor units sometimes have old installations, low ceilings and statutes that limit smoke and noise.
- On the coast, salt air punishes joinery, signs and outdoor units, which affects materials and maintenance though not the procedure.
- In tourist towns, the season dictates when it makes sense to open, and municipal timescales are felt more.
- Each town hall has its own ordinance and forms; some offer online filing and others ask for an appointment.

Always check with the town hall of your municipality whether there is a specific ordinance for activities and what documents it asks for. Do not rely on information from another municipality.

## Common mistakes

- **Signing the lease without checking the permitted use.** If the unit does not allow your activity, the works will not fix it.
- **Starting works with no municipal title.** It can end in a stop order and a fine, and in weeks of rent paid without opening.
- **Hiring the builder before the project.** If the project changes the layout, the works quote stops being valid.
- **Forgetting the community of owners.** Smoke, signs and outdoor units affect common elements.
- **Not asking for the installation documents.** Without certificates and reports, opening cannot be closed.
- **Announcing an opening date before you have the licence.** No builder controls the town hall's timescales.
- **Confusing the opening notification with a granted permit.** Filing the procedure does not mean the town hall has checked anything.

## When to call a professional

**Almost always.** Although the owner files, the technical part must be signed by a competent professional, and the works and installations must be carried out by someone who can certify them. What you can do yourself: gather the lease or deeds of the unit, check the statutes, define your activity and expected capacity clearly, and line up the timing of your suppliers.

Call the technician before signing the lease if you have doubts about the use, and the builder once you have the project so you receive a fixed quote that can be compared.

## Documents worth having to hand

**Gathering the papers early saves weeks, because almost every procedure asks for the same documents.** Before you talk to the technician, prepare what depends on you:

- Lease or deeds of the unit, with the cadastral reference.
- Tax details of the business owner, whether an individual or a company. If you are a foreign resident, your gestor can advise on NIE and registration.
- Statutes of the community of owners, if the unit is in a building with homes.
- A clear description of the activity, with planned hours, estimated capacity and whether there will be music, a kitchen or alcohol sales.
- Plans or photographs of the current state, if they exist from an earlier stage of the unit.
- Previous licences or notifications for the unit, if the landlord has kept them.

With this the technician can tell you in one visit whether there are obvious obstacles. For anything you do not have, they will tell you how to obtain it.

## How long the whole process usually takes

**The total time is the sum of project, procedure, works and opening, and it is almost never just the works.** The works on a unit take 4 to 10 weeks, but before and after there are stages that no builder controls. As an order of magnitude, think in months rather than weeks from choosing the unit to opening, and confirm the real timescales of your town hall with your technician.

Two practical tips: ask the landlord for a rent-free period for as long as the procedures take, and do not order signage, stock or staff for a fixed date until you have the opening go-ahead.

## Next step

If you already have the unit or are about to choose one, we visit within 48 to 72 hours, review what needs doing and give you a fixed quote by item, free and without obligation. See how we work in [commercial renovation in Alicante](/en/commercial-renovation-alicante/) and our page on [shop renovation](/en/shop-renovation-alicante/), read the Spanish page [proyectos y licencias de obra](/proyectos-licencias-obra-alicante/), and book your visit through the [contact page](/en/contact/).